Preparation and Setup
9/16/20
7000 Series 556-433M
15
First time Field Adjustments
Pre-Leveling of Machine
Note: Pre-leveling of machine should be done on a good
level surface (preferably concrete). Insure all tire
pressure is set to recommended pressure. Raise
machine and hold lever to insure that the air has
been purged from the lines.
1. Lower machine till blades are just off the ground,
adjust the hitch turnbuckle until the front and rear
blades are equal distance to the ground.
Scraper Adjustment
2. To adjust the disk scrapers loosen the u-bolts (1) that
hold the disk scrapper assembly (2) to the scraper
tube (3) and move the scraper until it is about
1
8
”
from the disc blade.
Figure 9
Scraper Adjustment
TP-69483
1
2
3