background image

1. Read all safety precautions and follow L. B. White

recommendations when installing this heater.  If

during the installation or relocating of heater, you

suspect that a part is damaged or defective, call a

qualified service agency for repair or replacement.

2. Make sure the heater is properly positioned before

use.  Observe and obey all minimum safe distances of

the heater to the nearest combustible materials.

Minimum safe distances are given on the heater

nameplate and on page 4 of this manual.

3. The heater is approved for indoor use only.

4. The heater shall be installed so that it is not directly

exposed to water spray, rain, and dripping water.

5. Certified construction heaters include a gas hose and

single-stage regulator.  The single-stage regulator is to

be used only in applications where temporary use of

the heater is required.  Contact the L.B. White Co. or

your fuel gas supplier if you have questions.

6. For permanent heater installations, two-stage gas

regulation is required.  The heater’s second-stage

regulator (with pressure relief valve) should be

installed outside of building.  Any regulators inside the

buildings must be properly vented to the outside.

Local, state and national codes always apply to

regulator installation.  Natural gas regulators with vent

limiting device may be mounted indoors without

venting to outdoors.

7. Insure that all accessories that ship within the heater

have been removed from inside of heater and

installed.  This pertains to air diverters, hose,

regulators, etc.

8. Make certain that a sediment trap is installed near the

gas valve inlet to prevent foreign materials (pipe

compound, pipe chips and scale) from entering the

gas valve.  Debris blown into the gas valve may cause

that valve to malfunction resulting in a serious gas

leak that could result in a possible fire or explosion

causing loss of products, building or even life.  A

properly installed sediment trap will keep foreign

materials from entering the gas valve and protect the

safe functioning of that important safety component.  

9. Any heater connected to a piping system must have an

accessible, approved manual shut off valve installed

within six feet (6 ft.) of the heater it serves.  

10. Check all connections for gas leaks using approved

gas leak detectors.  Gas leak testing is performed as

follows: 

-- Check all pipe connections, hose connections,

fittings and adapters upstream of the gas

control with approved gas leak detectors.  

-- In the event a gas leak is detected, check the

components involved for cleanliness and

proper application of pipe compound before

further tightening.  

-- Furthermore tighten the gas connections as

necessary to stop the leak.  

-- After all connections are checked and any

leaks are stopped, turn on the main burner.  

-- Stand clear while the main burner ignites to

prevent injury caused from hidden leaks that

could cause flashback.  

-- With the main burner in operation, check all

connections, hose connections, fittings and

joints as well as the gas control valve inlet and

outlet connections with approved gas leak

detectors.  

-- If a leak is detected, check the components

involved for cleanliness in the thread areas and

proper application of pipe compound before

further tightening.

-- Tighten the gas connection as necessary to

stop the leak.  

-- If necessary, replace the parts or components

involved if the leak cannot be stopped.

-- Ensure all gas leaks have been identified and

repaired before proceeding.

11. A qualified service agency must check for proper

operating gas pressure upon installation of the heater.

12. Light according to instructions on heater or within

owner's manual.

13. It is extremely important to use the proper size and

type of gas supply line to assure proper functioning of

the heater.  Contact your fuel gas supplier for proper

line sizing and installation.

WARNING

Fire oor eexplosion hhazard.

Can ccause pproperty ddamage, ssevere iinjury oor ddeath.

1. Disconnect power supply before wiring to prevent

electrical shock or heater damage.

2. To avoid dangerous accumulation of fuel gas, turn

off gas supply at the heater service valve before

starting installation, and perform gas leak test after

completion of installation.

7

Installation Instructions

GENERAL

WARNING

Fire aand EExplosion H

Hazard

Do not use open flame (matches, torches, candles,

etc.) in checking for gas leaks.  

Use only approved leak detectors.  

Failure to follow this warning can lead to fires or

explosions.

Fires or explosions can lead to property damage,

personal injury or loss of life.

Summary of Contents for PALS

Page 1: ...d is listed and approved as a direct gas fired convection construction heater with intended use for primarily the temporary heating of buildings under construction alteration or repair As an alternati...

Page 2: ......

Page 3: ...l injury or loss of life GENERAL HAZARD WARNING Failure to comply with the precautions and instructions provided with this heater can result in Death Serious bodily injury or burns Property damage or...

Page 4: ...ifications Contact PALS Wilmar Poultry at 1 800 328 8842 or the L B White Co Inc for assistance or if you have any questions about the use of the equipment or its application The L B White Co Inc has...

Page 5: ...ES 4 ft BOTTOM 4 ft GAS 6 ft SUPPLY 1 83 m 32 F 16 19 CV250 Propane Natural Vapor Gas M Mo od de el l Ventilation Air Required to Support Combustion CFM Net Weight lbs Shipping Weight lbs Inlet Gas Su...

Page 6: ...y trained service people must repair the leak check for further leakages and then relight the appliance for you WARNING Do not use this heater for heating human living quarters Do not use in unventila...

Page 7: ...r 8 Do not block air intakes or discharge outlets of the heater Doing so may cause improper combustion or damage to heater components leading to property damage or animal loss 9 The hose assembly shal...

Page 8: ...in six feet 6 ft of the heater it serves 10 Check all connections for gas leaks using approved gas leak detectors Gas leak testing is performed as follows Check all pipe connections hose connections f...

Page 9: ...res must be eliminated and defective parts replaced immediately The heater must be retested by properly qualified service personnel before placing the heater back into use HANGING INSTRUCTIONS A Hangi...

Page 10: ...f 100 lb cylinders Up to 3 cylinders maximum ASME Tank 500 Gallon 1 000 Gallon This type of regulator installation is typically associated with heaters utilized in a construction application FIG 3 B I...

Page 11: ...ond trial for ignition If burner flame is not established the igniter will stop sparking and the heater will shut down To recycle the heater for ignition Position On Off switch to Off and then back to...

Page 12: ...able vapors a and l liquids 3 Regulators can wear out and function improperly Have your gas supplier check the date codes on all regulators installed and check delivery pressures to the appliance to m...

Page 13: ...Disconnect the electrical leads from the On Off switch 2 Remove the rubber boot from the On Off switch See Fig 6 3 Remove the switch from the control box FIG 6 IGNITION CONTROL VOLTAGE REGULATOR NUT...

Page 14: ...OR 1 Open access door on barrel 2 Remove retaining pin and side panel from main burner assembly See Fig 12 3 Disconnect flame sensor and ignition leads Remove nuts and screws 4 Remove heat shield and...

Page 15: ...burner orifice from heater 6 Remove burner orifice from manifold 7 Position the orifice as shown in Fig 11 FIG 11 GAS CONTROL VALVE 1 Remove gas hose from heater 2 Remove control box cover and solenoi...

Page 16: ...section of this owner s manual 2 Does the pressure reading agree with that given on the dataplate If so no further checking or adjustment is required Proceed to section D 3 If the pressures does not...

Page 17: ...ied by the flow chart OPERATION SEQUENCE A call for heat occurs from building thermostat 24 Volts D C is sent from building s temperature control to heater s voltage regulator Voltage regulator reduce...

Page 18: ...pplying 12 Volts D C to Ignition Control Check Switch for Continuity Replace if Defective No 17 Is Fuse in Heater Receiving Proper Voltage Incoming Power Supply Should be 18 30 Volts D C Repair as Nec...

Page 19: ...ifice Clean Check the Lead for Corroded Terminals Loose Connections Repair or Replace as Necessary No No No Clean the Orifice Yes Is Sensor Reasonably Clean Properly Gapped Clean Sensor with Emery Clo...

Page 20: ...E BLUE BLACK HIGHVOLTAGE IGNITION LEAD CASE GROUND IGNITOR FLAME SENSOR ELECTRICAL CONNECTION DIAGRAM IF ANY OFTHE ORIGINALWIRES AS SUPPLIEDWITHTHE HEATER MUST BE REPLACED IT MUST BE REPLACEDWITHWIRIN...

Page 21: ...e Component that houses an electromagnet which is energized by voltage and therefore opens or closes to supply or close off the flow of gas to the burner Gas Hose Flexible connector used to convey gas...

Page 22: ...cation PARTS SCHEMATIC 24 35 34 22 36 37 33 32 30 27 23 26 25 53 50 41 45 29 28 31 49 43 44 38 51 52 55 54 14 17 48 40 39 18 15 8 10 5 4 56 57 13 11 12 3 6 9 16 20 19 2 46 7 21 47 42 1 29 5 17A 10A 1...

Page 23: ...ssembly 22641 19 Fuse Holder 21653 20 Cap Fuse 21655 21 Terminal Block 22296 22 Ignition Lead 22651 23 Cord Power 22653 24 Switch Toggle 22714 25 Holder Fuse 22762 26 Fuse 1 5 Amp 250 V 22763 27 Boot...

Page 24: ...d date o of p purchase b by the e end u user Warranty is automatic if a component is found defective within 12 months of the date code marked on the part If the defect occurs more than 12 months late...

Reviews: