Installation Overview Gas 310 ECO
2
Information
1. With the 310 harness installed into the power
supply from previous steps, route wiring across
back of control.
2. Locate the K1 plug and press in the connector
of the power supply harness into the K1 plug of
the control.
3. Find the flat ribbon cable in the boiler wiring
harness and connect one of the multi plugs into
the mating socket on the interface. Note that
the ribbon cable will have many plugs
attached that can be connected to other
accessory boards. Use nearest plug without
straining the cable against any other plug.
Once all of the connections have been verified, the
power switch of the control can now be turned on
to perform the communication testing of the
gateway. With the BMS plug-in connection to the
gateway complete, it should be possible to start
reading information from the boiler control.