5 Installation at Site
24 of 62
SRA
2334.810/03-EN
5.4 Installing the valve pit (optional)
CAUTION
Clogging of the piping / formation of air pockets
Damage to the pump station!
▷
The height of the discharge connection of the valve pit has to be equal to or
above the height of the discharge nozzle of the collecting tank.
Fig. 13:
Positioning the valve pit in the construction pit
ü
The construction pit has been properly prepared. (
ü
The collecting tank has been installed properly. (
ü
Transport equipment / lifting equipment suitable for the corresponding weight
(see data sheet) has been selected and is on hand.
ü
The data sheet (scope of supply) is available.
1. Lower the valve pit into the construction pit with suitable transport equipment /
lifting equipment (e.g. digger or crane).
2. Position and level the valve pit and verify the permissible height difference
against the data sheet. The height of the discharge connection of the valve pit
has to be equal to or above the height of the discharge nozzle of the collecting
tank. Balance out the height difference if necessary.
Fig. 14:
Permissible installation position of the valve pit in relation to the collecting
tank