8. Verify that the pump is running smoothly.
9. Close the discharge-side shut-off element in order to verify whether the pump
reaches its maximum shut-off head.
10. Make sure that the dry running protection device is working properly.
NOTE
Minor leakage of the mechanical seals during commissioning is normal and will
cease after a short period of operation.
6.2 Switching on the pressure booster system
Plug in the mains plug or set the master switch to I to energise the pump.
Readiness for operation is signalled by a permanently lit red LED and a flashing green
LED.
6.3 Checklist for commissioning/start-up
Table 10:
Checklist
Actions
Done
1
Read the operating manual.
2
Compare the power supply data against the name plate data.
3
Check the earthing system (taking measurements).
4
Check the mechanical connection to the water mains.
Re-tighten the flange bolting and pipe unions.
5
Prime and vent the pressure booster system from the inlet side.
6
Check inlet pressure.
7
Check the start-up pressure, re-adjust if necessary.
8
Test the proper function of the lack-of-water and dry running protection equipment.
9
Vent the pump for a second time after it has been running for 5 to 10 minutes.
10
Check the pre-charge pressure.
11
Record all system conditions that do not correspond to our specifications or to the purchase
order in the commissioning report (i.e. inlet pr max. pressure of pressure booster
system higher than 16 bar).
12
Complete the commissioning report together with the operator/user and instruct the operator/
user as to the function of the unit.
6.4 Shutdown
NOTE
As long as the pressure booster system is out of operation, water is supplied directly
at p
inl
through the pressure booster system.
Summary of Contents for Delta Solo Compact MVP Series
Page 38: ......
Page 39: ......
Page 40: ...KSB B V Kalkovenweg 13 2401 LJ Alphen aan den Rijn Netherlands 1983 848 01 EN ...