Make sure the scrap screen and spray arm are in place.
Initial Start-up
Check List
1.
Make sure the glasswasher is permanently located.
2.
Make sure all utility connections are complete.
3.
Make sure the flexible drain hose and the hot water fill hose are not kinked.
4.
Remove any protective film from glasswasher.
5.
Check the interior for foreign material.
6.
Remove the scrap screen and check the sump for foreign material.
7.
Make sure the chemical supply containers are full and that the chemical pick-up tubes
are installed in the proper containers.
8.
Make sure the scrap screen is in place.
9.
Make sure the spray arm is in place and that it spins freely.
10.
Close the glasswasher door.
11.
Turn hot water supply on and check for leaks in the main water supply piping connected
to the glasswasher.
Scrap
Screen
Spray Arm