K20s
- 70 -
The establishment of precision engineering control network, such as bridge measurement, tunnel
measurements, etc;
The establishment of a variety of encryption control network, such as city measurements,
Drawing Point measurement, road surveying, demarcation measurements.
For the GPS measurements of small and medium-sized cities, towns, as well as mapping,
cadastral, land information, real estate, geophysical exploration, surveying, construction and
other control measurement, should meet the accuracy requirements of the D, E grade GPS
measurements.
§6.1.2 Operating Procedures
Pre-measurement
Project approval
Program design
Construction design
Surveying and mapping data collection and arrangement
Instrument test, test
Reconnaissance, choice of site, buried stone
Measurement
Operating team stationed in
Satellite status Forecast
Observation planning
Dispatch of operation and field work observation
After the measurement
Data transmission, dump, backup,
Baseline Solution and quality control
Network adjustment (data processing, analysis) and quality control
Finishing results, technical summary
Project acceptance
§6.1.3 Field Operation Notes
1)Static mode of KOLIDA K20s receiver can be set in EGStar software or other software (Such
as SurvX, Field Genius or SurvCE), also can be performed by receiver keypad.
2)Set up a tripod on the control point, leveling and centering strictly on the measuring point.
3)Measure the instrument height three times, the difference of the results shall not be more than
3 mm, and average the results. The instrument height should be measured from the center of the
control point to the mark line on the instrument.(Refer to §3.4)
4)Record instrument number, point name, instrument height, and start time.