TP-6835 9/17
64
Section 7 Bypass, Isolation, and Manual Transfer
7.3.2
Isolating the ATS,
800--1200 Amp Models
Isolate the transfer switch before performing any service
work on the automatic transfer switch (ATS). Refer to
Figure 7-39 through Figure 7-42.
1. Bypass the closed automatic transfer switch
contacts. See Section 7.3.1 for instructions.
2. Turn the Isolation Handle counterclockwise
(approx. 8 turns) until window shows
TEST
. See
Figure 7-39. The
TS Test
amber light should come
on (Figure 7-40). The ATS can be tested now
without load interruption.
Note:
In the TEST position the transfer switch solenoid
operator circuit is energized through secondary
disconnects.
Position
window:
CONN
TEST
ISOLATE
Counterclockwise – draws
out the transfer switch
Figure 7-39
Isolation Handle Turned to TEST
E
L
N
Automatic Transfer Switch
Bypass Switch
Turn crank
counter-
clockwise
until window
shows TEST.
TS CONNECTED
Middle amber light
should be on.
TS TEST
TS ISOLATED
Figure 7-40
CONNECTED to TEST position
3. Continue
turning
the
Isolation
Handle
counterclockwise (approx. 6 turns) until the
window shows ISOLATE. See Figure 7-41. The
amber TS Isolated light should come on
(Figure 7-42).
Position
window:
ISOLATE
Counterclockwise – draws
out the transfer switch
Figure 7-41
Isolation Handle Turned to ISOLATE.
Summary of Contents for KBC
Page 26: ...TP 6835 9 17 26 Section 2 Installation Notes...
Page 44: ...TP 6835 9 17 44 Section 4 Communication and Accessory Connections Notes...
Page 48: ...TP 6835 9 17 48 Section 5 Functional Tests and Setup Notes...
Page 50: ...TP 6835 9 17 50 Section 6 Scheduled Maintenance Notes...
Page 76: ...TP 6835 9 17 76 Section 7 Bypass Isolation and Manual Transfer Notes...
Page 79: ......