www.grupotemper.com 25
KPAW-01
TRUE RMS 1000A AC WATT Clamp Meter
Figure 15
1. Insert red test leads to
L1, L3
input terminal.
2. Insert black test leads to
COM
input terminal and connect
it to the neutrual wire of the 3 phase.
3. Jump over the second phase measurement.
4. The first and the third phase measuring method is same
as 3 phase 4 wires.
In figure 15
∑
W = W2 + W3.
NOTE
It can only sum up the current measurement value. The
maximum and minimum value cannot be summed up.
Only at
KW
range can carry out sum of watts
measurement, other ranges cannot carry out this
measurement.
When testing has been completed, disconnect the
connection between the testing leads and the circuit under
test and remove testing leads from the input terminals.
Red
Yellow
Blue