2.4  A fire hazard 

With  insertion-type  firing  systems,  the  conveying  route 
creates a connection between the silo and the burning ma-
terial in the boiler plant. 
With the PYROT

 

insertion-type heating boiler, the feed au-

ger is also the metering auger, and is thus always filled up 
with  material  during  operation  There  are  various  safety 
devices provided to prevent burn-back. 
Temperature sensors: 
By  means  of  temperature  sensors  on  the  feed  auger,  in 
case of excess temperature the loading to the feed auger 
is  interrupted,  and  the  feed  auger's  material  is  inserted 
into the combustion chamber. 
Slide valve (optional): 
This closes in case of a standstill, danger of burn-back or 
power failure (spring return motor). 
valve (optional): 
Instead of a slide valve, in silos with pressurisation.  
Drop-off route: 
A vertical drop-off section interrupts the connected line of 
burning material. 
Fire-extinguishing system (option): 
This system, which functions independently of the electri-
cal  power,  brings  about  a  flooding  of  the  material  to  be 
burned  that  is  located  in  the  feed  auger.  The  activation 
temperature is approx. (95°C) 200°F. 
 

2.5  Wood fuels, minimum requirements 

The PYROT is only suitable for incinerating the fuels listed 
in  Spec  Sheet  1010  "Minimum  Requirements  for  Wood 
Fuels" (see supplement). 
 

If different fuels are used, Viessmann will not assume any 
liability  for  the  functioning  or  service  life  of  the  boiler 
plant.    Refer  to  the  "Warranty"  section  in  the  General 
Terms and Conditions of Delivery. 

 

Born wood only 

Do not use chemicals or fluids to start fire. 

Do not burn garbage, gasoline, naphtha, engine oil, or 
other inappropriate materials. 

2.6  Filling the fuel storage unit 

When storage facilities for wood are required, the wood 
should be kept at least (1.5m) 5ft from the heating appli-
ance. 

2.6.1  By dumping 

Rotary sweep extraction and spring-operated extraction 

Heating system in operation:  

If the articulated arms or spring-mounted plates are still 
covered  by  fuel,  refilling  can  be  carried  out  immedi-
ately.  

If the articulated arms or spring-mounted plates are no 
longer  covered  by  fuel,  fill  the  silo  evenly  to  approx. 

(30  cm)  1ft  above  the  articulated  arm  or  over  the 
spring-mounted  plates.    As  soon  as  the  articulated 
arms  or  spring-mounted  plates  have  retracted  through 
a request for material, the refilling can be continued.  

Heating out of operation: 

If the articulated arms or spring-mounted plates are still 
covered  by  fuel,  refilling  can  be  carried  out  immedi-
ately. 

If the articulated arms or spring-mounted plates are no 
longer  covered  by  fuel,  fill  the  silo  evenly  to  approx. 
(30  cm)  1ft  above  the  articulated  arm  or  over  the 
spring-mounted  plates.  Then  activate  the  "SILO  FILL-
ING"  function.  To  do  so,  press  the  LOADER  SYSTEM 
key  (F4)  and  then  the  left arrow key (<). Then select 
"YES"  and  confirm  with  "OK".  Wait  until  the  articu-
lated  arms  or  the  spring-mounted  blades  go  under  the 
cup washer, and then finish evenly filling the silo. The 
"SILO FILLING" function brings about the filling of the 
fire box.   

 

NOTE:  The  "SILO  FILLING"  function  cannot  be  activated 
until the heating system has been out of operation for one 
hour.  

 

Moving floor conveyor 

Fuel can be refilled automatically.  

Funnel extraction system 

It  is  mandatory  that  the  heating  system  be  in  opera-
tion! 

2.6.2  By blowing in 

The heating system has to be out of operation (danger of 
excess pressure or negative pressure caused by the action 
of  blowing-in).  Filling  procedure  as  described  in  section 
2.6.1. 

 

2.7  Correcting malfunctions in the feed systems 

The  cause  of  motor  malfunctions  in  feed  systems  is  usu-
ally clogging by large pieces of wood or foreign matter. 
 

CAUTION 
DANGER OF INJURY: 
Always turn off the master switch before carrying out any 
repair  of  a  malfunction  on  feed  systems  and  every  time 
before  a  maintenance  lid is opened or a protective  device 
is removed! 

 
The  automatic  operation  of  the  system  makes  it  impossi-
ble  to  foresee  the  time  point  when  the  conveying  equip-
ment will switch on. 
 

 

Summary of Contents for PYROT KPT 1250

Page 1: ...Open windows and doors Inform your heating contractor Installation and service must be performed by a installer or service agency If the information in this manual is not followed exactly a fire o r e...

Page 2: ...nually before the heating season begins Contaminated air Air contaminated by chemicals can cause by products in the combustion process which are poisonous to inhabitants and destructive to Viessmann e...

Page 3: ...ed skin Wash area of contact thoroughly with soap and water Using a skin cream or lotion after washing may be helpful Gastrointestinal irritation If gastrointestinal tract irritation develops move the...

Page 4: ...nformation Warnings draw your attention to the presence of potential hazards or information Cautions draw your attention to the presence of potential hazards or important product information Helpful h...

Page 5: ...4 Commissioning Operation ________________________________________________ 15 4 1 The initial start up _____________________________________________________________________ 15 4 2 Operation _________...

Page 6: ..._________ 27 6 2 Installing the displacement rods into the heat exchanger __________________________________ 29 6 3 Feed systems________________________________________________________________________...

Page 7: ......

Page 8: ...nt Open windows and doors Inform your heating contractor Combustion air and ventilation air openings Ensure that combustion air openings and ventilation air openings in the mechanical room are open Te...

Page 9: ...ldings that contain gas burning equipment Note Viessmann does not test any detectors and makes no representation regarding any brand or type of de tector For safe operation We recommend that you frequ...

Page 10: ...aps and toilet tanks Open faucets where appropriate Or Have someone check the building frequently dur ing cold weather and call a qualified service agency if required Or Install a reliable remote temp...

Page 11: ...in clothes dryers Product information High efficiency with reduced emissions Viessmann solid fuel boiler may only be set up and commissioned by specialists This will rule out any incorrect assembly o...

Page 12: ...ulated in the regulations of the Assembly and Installation In structions by the limits of the technical specifications in Spec Sheet 1010 Minimum Requirements for Wood Fuels Instructions by the safety...

Page 13: ...ated and maintained properly can even the best of products fulfil their functions well doing so for a long time and free of malfunctions Compliance with the Cleaning section is mandatory 2 2 Excess te...

Page 14: ...operation If the articulated arms or spring mounted plates are still covered by fuel refilling can be carried out immedi ately If the articulated arms or spring mounted plates are no longer covered by...

Page 15: ...stem 5 Moving grate 6 Drive for automatic de ashing system optional 7 Rotation fan Viessmann patented 8 Rotation combustion chamber Viessmann pat ented 9 Boiler heat exchanger 10 Boiler door 11 Heat e...

Page 16: ...ignition then takes place The ignition process stops as soon as the fire is started 4 2 2 Operation The material is supplied depending on the light barriers in the metering container and in the combus...

Page 17: ...OIL OPERATION on and off F3 PYROT Parameters Setting parameters set point values the date and time F4 PYROT Loader System Setting of cycle switchover switching advance flow and post flow times F5 Gro...

Page 18: ...Minimum YES Service Menu 14 Load storage unit to STORAGE UNIT AT BOTTOM To which heat storage sensor should the storage unit be loaded with wood operation Indication only for storage unit option 15 L...

Page 19: ...fore connecting Conveyor System 1 e g spring operated extraction system inclined extraction system etc 39 Extraction System 1 Impulse 5 s Impulse for the cycle switching for Extraction System 1 e g sp...

Page 20: ...elects the day pressing the button again drops the day 04 Heating Period 1 Start 6 00 Time to switch from lowered temperature or off to nor mal temperature 05 Heating Period 1 End 22 00 Time to switch...

Page 21: ...N T Point 2 always has to be set higher than Point 1 The two points marked indicate the factory setting Point 1 is set to 43 C and Point 2 to 64 C This is equivalent to a steepness of approx 1 5 Room...

Page 22: ...up during the heating pe riod On The boiler is heated up when prompted for heat and when there is sufficient system temperature Manual Pump on the valve is not controlled emergency opera tion screen...

Page 23: ...tered in the form of heating periods Each weekly programme consists of the heating day start and end A maximum of seven heating periods is available 03 Heating Period 1 Heating days MON to SUN Day or...

Page 24: ...days with KEYS F1 for Mon day to F7 for Sunday Pressing the button once selects the day pressing the button again drops the day 04 Heating Period 1 Start 6 00 Time to switch from lowered temperature...

Page 25: ...y Pressing the button once selects the day pressing the button again drops the day 37 Heating Period 1 Start 6 00 Start clearance utility water heating 38 Heating Period 1 End 22 00 End clearance util...

Page 26: ...screen number parameter factory setting 01 Operating mode automatic Select operating mode 02 Delay before connecting 15 min Clearance is given when the time set is up 03 Connecting temperature system...

Page 27: ...which is then in operation with the solar pump For optimised functioning the flow rate in the sec ondary circuit has to be adapted to the primary circuit e g with flow rate gauges in the primary and...

Page 28: ...ing hours Remove ash from the ex haust gas collector After approx 1000 operating hours Unplug the plug from the exhaust gas fan unscrew butterfly nuts pull out motor with impeller and clean with broo...

Page 29: ...s operation or be secured against continuous op eration e g timer for limiting running time Continuous operation of the compressor indicates leak age in the air system Check air supply line and valves...

Page 30: ...ubes and then put back in Insert the displacement rods into the heat exchanger tube with the thick end first Push until they are flush with the bottom of the tube Tolerance 5 mm Remove the displacemen...

Page 31: ...ere is a danger of frost empty the heating system following the heating installer s rules or have anti frost agent filled Control system Even when the PYROT is put out of operation for long pe riods t...

Page 32: ...with pre dryer max 4 0 of the total mass consequence of substantial overstepping of limit Moving the exhaust air lines Special maintenance instructions for cleaning exhaust air line 3 Origin and trea...

Page 33: ...al mass The maximum water content allowed in the fuel when entering the furnace should be taken from the spec sheets for the furnace series With a pre dryer installed between the furnace and the fuel...

Page 34: ...nition device defective The combustion chamber filling time is too short Use suitable dry fuel Readjust lambda sensor Replace ignition device Readjust combustion chamber Acknowledge with OK 20 Water l...

Page 35: ...red Maintenance cover limit switch One of the maintenance covers is open or not closed properly Check and close all the maintenance covers Acknowledge with OK 51 52 Extraction system F4 lights up red...