OPERATION
(1) [Fig. A] Fill the foamer tank with a combination of
water and foaming chemical — consult your chemical
supplier for proper dilutions. Do not overfill tank.
(2) [Fig. B] Close Wet Foam/Dry Foam Valve completely
— turn clockwise until it stops.
(3) [Fig. C] Make sure the ball valve on the discharge
hose is closed!
(4) [Fig. D] Connect a clean, dry, air supply to the
5/16” quick connect fitting on the unit. Note: Unit
will operate when air supply is on.
(5) [Fig. C] Slowly open the ball valve on the discharge
hose while holding foam wand away from you.
Closing the ball valve will turn pump off.
(5) [Fig. E] Adjust air pressure regulator to achieve
desired pump flow rate (between 60—80 PSI for
optimum results).
(6) [Fig. B] Open Wet Foam/Dry Foam Valve in the
counter-clockwise direction four complete turns.
(7) [Fig. B] Continue to open the Wet Foam-Dry Foam
Valve in ¼ turn increments, allowing a few seconds
between adjustments, until the proper consistency
(dryness) of foam is achieved.