2 .3 .3 Additional Installation Hints
ATTENTION
U
The 16
2
PE lines have to be high-flexible to derive the high-frequency ignition
voltage.
U
Do not use the wires in the lamphouse cable to connect the additional dowser.
Lay the dowser connection in the lamphouse tube as short as possible.
U
If you install an old building projector remove all not used old cables, wires and lines
under the projector.
U
If possible the heat exchanger must not have more than 10 m distance to the
projector and the refrigerating set must not have more than 15 m distance to the
heat exchanger. If the environment temperature is high and the wires are long, the
hose is to be isolated because of condensation.
U
The cooling water temperature has to be more than 15° C, to avoid a precipitation of
condensed water on the film gate and the front gate.
2 .3 .4 Installing and Connecting the Lamphouse Components
X
NOTE
Z
Connecting the lamphouse should be carried out by service personnel.
Z
The installation and adjustment of the xenon bulb and the adjustment of the intensity
of currents is described in chapter 6.4.
Z
The mirror should only be installed and adjusted by trained service personnel.
The reflector should only be changed and adjusted roughly by the projectionist in
case of need, therefore see chapter 6.4.
Z
Installing the heat filter is described in chapter 6.4.
Z
You will find the lamphouse connecting plan in chapter 8.