Kingspan BF BIODISC Installation Manuallines Download Page 8

GL0016P-02 Installation Guidelines for BioDisc

®

 Units BF, BG, NF & NG 

 

 

8

5.11   Place concrete backfill to approximately 500mm depth around the unit ensuring good compaction to 

avoid voids. 

Do not use vibrating pokers.

   

5.12   Continue backfilling with concrete up to the level of the outlet.  Keep the concrete at an even level all 

round the unit, compacting in layers. As backfilling progresses keep the ballast water level inside the 
unit 250-500mm above the concrete backfill level, but do not attempt to fill the unit with water above 
the outlet level. 

5.13   BG and NG only: Ensure that concrete is fed into the area between the two casings to eliminate voids 

as far as possible and assist in anchoring the unit. 

5.14   Connect the inlet and outlet pipework when safe access can be gained. Short lengths of “rocker” pipe 

with flexible joints should be used adjacent to the unit to allow for any minor differential movement. 

5.15   Check the cables attached to the control panel and drill the corresponding number of 40mm holes in 

the BioDisc case, 100mm below ground level and adjacent to one end of the interior walkway. If an 
Independent Remote Alarm is to be fitted this will also require a 40mm hole. 

5.16   Erect the Control Panel as described in Section 6.0. 
5.17   Continue  backfilling to ground level with concrete, pea shingle (3-18mm), or similar non-cohesive, 

non-compressible free-flowing granular material.  

Do not use sand.

  The finished surface should be 

65mm minimum lower than the lip of the cover. 

5.18 

  Important :  Read section 8.2 regarding delayed electrical installation

 

6.0      Control Panel Installation 

6.2.   General Installation 

6.1.1.  The control panel should be positioned adjacent to the unit, so that: 

a)  It does not interfere with cover removal. 
b)  It is convenient for the incoming power supply. 
c)  It cannot be reached by someone standing in or on the BioDisc unit. 
d)  It is close enough to enable the electrical connections to be made in the BioDisc. 
This usually indicates a panel position about 1.5 metres distance from the BioDisc, adjacent to the 
inlet or outlet. 

6.1.2.  Set the panel leg(s) in a concrete base, minimum 250mm thick and prop the panel to prevent 

movement until the concrete has set.  Allow 350mm minimum clearance from ground level to the 
bottom of the panel. 

6.1.3. Control panels are supplied with pre-fitted steel wire armoured (s.w.a.) cable(s), complete with 

grommets and glands. Lay the cable(s) in a 500mm deep trench and bed them on a layer of sand or 
similar soft material. 

6.1.4.  Insert the cables through the hole(s) in the casing of their respective unit(s), using the grommets 

supplied.  Leave the cable(s) temporarily secured above water level pending electrical installation. 

6.1.5.  Cover the cable(s) with a layer of sand or similar soft material and warning tape. Backfill the cable 

trench with graded spoil, free of large stones or any other material which might damage the cable(s). 

6.1.6.  The Control Panel key is in the protective bag at the end of the motor/gearbox cable.

 

 

6.2. Electrical 

Installation 

6.2.1. Depending on type, the control panel is supplied with between one and three pre-fitted armoured 

cables. 

a)  Every Control Panel has a motor/gearbox cable. 
b)  Control Panels for NF, NG and BG units have an additional Sludge Return Pump cable. 
c)  Alarm Control Panels have an extra cable for the Loss of Rotation sensor. 
 
Each cable is fitted with a gland for connection to the terminal box or junction box and a grommet for 
entry into the BioDisc case. 
 

Summary of Contents for BF BIODISC

Page 1: ...ith in the control panel housing If additional copies are required contact Kingspan 510030P BF 3 Phase Control Panel Wiring Diagram 510003P BF 3 Phase Alarm Control Panel Wiring Diagram 510017P BF Sin...

Page 2: ...tails on request Should you wish to inspect the operation of the equipment please observe all necessary precautions including those listed below which apply to maintenance procedures BioDisc units con...

Page 3: ...GL0016P 02 Installation Guidelines for BioDisc Units BF BG NF NG 3...

Page 4: ...also inside units particularly if they have been stored on site prior to installation adding weight and increasing instability Check units before lifting and pump out any excess water 2 5 When lifting...

Page 5: ...though not obligatory for an installation of this type RCD protection is suggested as an extra precaution 3 12 Pump stations or any other associated equipment should have a separate power supply 3 13...

Page 6: ...support the installed load but not so much as to prevent subsequent backfill bonding fully to the base 5 4 Ensure that the slab is free of any stones or other material which could damage the unit Low...

Page 7: ...panel Customer Supply Inlet Pipe Control Panel G L 600mm Inlet Invert Add 100mm For Outlet Invert Concrete backfill minimum 150mm thick but to suit specific site conditions Concrete Pea Shingle or oth...

Page 8: ...control panel should be positioned adjacent to the unit so that a It does not interfere with cover removal b It is convenient for the incoming power supply c It cannot be reached by someone standing i...

Page 9: ...han 100 metres from the BioDisc and that the interconnecting cable customer supply should be laid in a separate trench to prevent electrical interference 6 2 5 Connect the incoming power supply to the...

Page 10: ...GL0016P 02 Installation Guidelines for BioDisc Units BF BG NF NG 10...

Reviews: