Kingspan BF BIODISC Installation Manuallines Download Page 2

GL0016P-02 Installation Guidelines for BioDisc

®

 Units BF, BG, NF & NG 

 

 

2

 

HEALTH AND SAFETY 

 
These warnings are provided in the interest of safety. You must read them carefully before installing or using the 
equipment.

 

It is important that this document is retained with the equipment for future reference. Should the equipment be transferred 
to a new owner, always ensure that all relevant documents are supplied in order that the new owner can be acquainted with 
the functioning of the equipment and the relevant warnings. 
Installation should only be carried out by a suitably experienced contractor, following the Guide-Lines supplied with the 
equipment. 
We recommend the use of a dust mask and gloves when cutting GRP components. 
Electrical work should be carried out by a qualified electrician. 
Sewage and sewage effluent can carry micro-organisms harmful to human health. Any person carrying out maintenance on 
the equipment should wear suitable protective clothing, including gloves. Good hygiene practice should also be observed. 
Covers must be kept locked. 
Observe all hazard labels and take appropriate action to avoid exposure to the risks indicated. 
The correct ongoing maintenance is essential for the proper operation of the equipment. Kingspan offer a range of 
maintenance contracts, details on request. 
Should you wish to inspect the operation of the equipment, please observe all necessary precautions, including those listed 
below, which apply to maintenance procedures. 
BioDisc units contain rotating machinery and associated drive chains or belts. 
Ensure that you are familiar with the safe working areas and accesses. 
Ensure that the working area is adequately lit. 
The power supply to the equipment must be isolated at the control panel(s) before lifting the covers. Where a specific 
maintenance procedure requires the equipment to be running with the covers off, all care must be taken to avoid contact 
with moving parts and electrical components or conductors. Drive guards must be replaced and secured if removed during 
maintenance. 
Once power has been isolated, the control panel must be kept locked shut to avoid accidental re-connection whilst work or 
inspection is being carried out. 
Use only the designated access walkways. Do not walk on the cover or deep well safety mesh(es). Desludge port covers, 
where fitted, must be replaced if removed. 
Take care to maintain correct posture, particularly when lifting. Use appropriate lifting equipment when necessary. Keep 
proper footing and balance at all times. Avoid any sharp edges.  
Desludging should be carried out by a contractor holding the relevant permits to transport and dispose of sewage sludge. 
The contractor must refer to the desludge instructions in the Operating Manual, a copy of which is fastened under the 
covers. 

Summary of Contents for BF BIODISC

Page 1: ...ith in the control panel housing If additional copies are required contact Kingspan 510030P BF 3 Phase Control Panel Wiring Diagram 510003P BF 3 Phase Alarm Control Panel Wiring Diagram 510017P BF Sin...

Page 2: ...tails on request Should you wish to inspect the operation of the equipment please observe all necessary precautions including those listed below which apply to maintenance procedures BioDisc units con...

Page 3: ...GL0016P 02 Installation Guidelines for BioDisc Units BF BG NF NG 3...

Page 4: ...also inside units particularly if they have been stored on site prior to installation adding weight and increasing instability Check units before lifting and pump out any excess water 2 5 When lifting...

Page 5: ...though not obligatory for an installation of this type RCD protection is suggested as an extra precaution 3 12 Pump stations or any other associated equipment should have a separate power supply 3 13...

Page 6: ...support the installed load but not so much as to prevent subsequent backfill bonding fully to the base 5 4 Ensure that the slab is free of any stones or other material which could damage the unit Low...

Page 7: ...panel Customer Supply Inlet Pipe Control Panel G L 600mm Inlet Invert Add 100mm For Outlet Invert Concrete backfill minimum 150mm thick but to suit specific site conditions Concrete Pea Shingle or oth...

Page 8: ...control panel should be positioned adjacent to the unit so that a It does not interfere with cover removal b It is convenient for the incoming power supply c It cannot be reached by someone standing i...

Page 9: ...han 100 metres from the BioDisc and that the interconnecting cable customer supply should be laid in a separate trench to prevent electrical interference 6 2 5 Connect the incoming power supply to the...

Page 10: ...GL0016P 02 Installation Guidelines for BioDisc Units BF BG NF NG 10...