5.2 Commissioning

Following the successful testing of all (and not just some) devices in 

the system you can proceed with the commissioning.

system  with  the  wiring  diagram,  drawing  or  photo  of  the  system, 

risks  analysis  and  solutions  adopted,  manufacturer  declaration  of 

conformity of all devices connected, instruction manual of each de-

vice and maintenance schedule of the system.

Fix on the gate or door a plaque indicating the automation data, the 

name of the person responsible for the commissioning, the serial 

number and year of construction, the CE mark.

Attach  a  plaque  indicating  the  steps  required  to  manually  unlock 

the system.

Implement and deliver to the end user the declaration of conform-

ity, the instructions and warnings for use for the end user and the 

maintenance schedule of the system.

Make  sure  the  user  understands  proper  automatic,  manual  and 

emergency operation of the automation. 

Inform the end user in writing of the dangers and risks still present.

5.1 Testing

All  system  components  must  be  tested  following  the  procedures 

outlined in the respective instruction manuals.

Check that they meet the guidelines in Chapter 1 - Safety warnings

Check that the gate or door can move freely once the automation 

is unlocked, and that they are in equilibrium and stationary if left in 

any position.

Check the correct operation of all connected devices (photocells, 

sensitive  edges,  emergency  buttons,  etc.),  testing  the  opening, 

closing and stopping of the gate or door via the connected control 

devices (transmitters, buttons, switches).

-

cians who must perform the tests required by relevant legislation 

related  to  risks,  ensuring  compliance  with  the  provisions  of  the 

testing methods for the automation of doors and gates.

5- TESTING AND COMMISSIONING THE AUTOMATION

Summary of Contents for BOOM GATE

Page 1: ...BOOM GATE Instructions and warnings for installation and use ...

Page 2: ...ct Introduction Technical characteristics Preliminary Checks Installing the Product Installing Release Adjustment of rod angle Inversion of direction of opening Balancing Testing and commissioning Testing Commissioning Instructions and warnings for TABLE OF CONTENTS ...

Page 3: ...d it must be replaced by the manufac turer or its after sales service or in all cases by a person with similar do not allow parts of the automation system to be immersed in water or other liquids During installation ensure that no liquids are able to enter the various devices should this occur disconnect the power supply immediately and contact a Key Automation Service Centre Use of the automation...

Page 4: ...barrier is well balanced and will therefore remain sta tionery when released in any position check that the electricity supply line to which the product is to be connected is suitably earthed and protected by an overload and dif ferential safety breaker device the system power supply line must include a circuit breaker device with a contact gap allowing complete disconnection in the condi ensure t...

Page 5: ...the allen wrench back to its original position and close the lock You can now restore the power supply and check that everything is working correctly Fasten the locking nut back in place 4 4 Changing the direction of opening ALT4 VERSION Turn off the power supply and with the manual manoeuvre place the rod vertical restore the transmission and remove the rod to pre vent hazardous conditions Open t...

Page 6: ...edule of the system Make sure the user understands proper automatic manual and emergency operation of the automation Inform the end user in writing of the dangers and risks still present 5 1 Testing All system components must be tested following the procedures outlined in the respective instruction manuals Check that they meet the guidelines in Chapter 1 Safety warnings Check that the gate or door...

Page 7: ...320 845 1110 900ALT624K 400 830 1188 280 900ALT242K 220 Fig 1 Dimensions IMAGES ...

Page 8: ...base Fig 4 IT Fissaggio barriera EN Fixing the barrier body DE Die Festsetzung der Sperrkörper ES Fijación barrera FR Fixation barrière PT Fixação barreira PL Mocowanie korpusu bariery Fig 2 Typical Installation ALT4 ALT6 ...

Page 9: ...Fig 6 Adjustment of rod angle Fig 5 Release Fig 7 Inversion of direction of opening and balancing ALT4 ALT6 ...

Page 10: ...Automation S r l Via A Volta 30 30020 Noventa di Piave VE T 39 0421 307 456 F 39 0421 656 98 info keyautomation it www keyautomation it Instruction version 580ISBR rev 01 580ISBR rev 03 Instruction version ...

Reviews: