Backfill the excavation pit
CAUTION
Note the structural calculations for traffic safety. Chamber installation for load class D makes a load distribution plate
made of reinforced concrete necessary (exception: not necessary for standard road construction).
Determine the required load class and structural calculations in accordance with the environment / use condi-
tions.
Request an appropriate reinforcement drawing from the KESSEL hotline.
(1)
Subbase (crushed stone)
(5)
Ground
(2)
Tank bed (sand)
(6)
Base course
(3)
Separator according to the structural calculations
(7)
Top of tank
(4)
Fill material (crushed stone)
(8)
Load distribution plate (for load class D)
Fill the excavations with crushed stone (0-16 mm diameter), at least 50 cm all around; place in layers of maximum 30 cm
and compact each layer of fill material properly to 97% Dpr (e.g. using vibrating plate).
At the same time, the tank must be filled with water so that a maximum difference of 30 cm exists between the liquid level
and the level of the fill material.
The required excavation pit slope angle β must be observed all the way round.
The assignment of internal frictional angle φ of the fill material, and permissible excavation pit slope angle β must be car-
ried out in accordance with EN 4124.
EN
010-223
Installation and operating instructions
29 / 108
Summary of Contents for EasyClean free NS 25
Page 18: ...DE 8 1 Anlagenpass 18 108 Einbau und Betriebsanleitung 010 223_01...
Page 35: ...8 1 System passport EN 010 223 Installation and operating instructions 35 108...
Page 52: ...FR 8 1 Fiche syst me 52 108 Instructions de pose et d utilisation 010 223...
Page 69: ...8 1 Scheda dell impianto IT 010 223 Istruzioni per l installazione e l uso 69 108...
Page 86: ...NL 8 1 Installatiepaspoort 86 108 Inbouw en bedieningshandleiding 010 223...
Page 103: ...8 1 Paszport techniczny PL 010 223 Instrukcja zabudowy i obs ugi 103 108...
Page 104: ......
Page 105: ......
Page 106: ...106 108 010 223_01...
Page 107: ...010 223_01 107 108...