HANGER BRACKETS & TRAP INSTALLATION

1) Remove hanger bracket fastened to back of cooler by removing one (1) screw. SEE FIGURE 

3.

2) Mount the hanger bracket to the wall.

NOTE:

 Hanger Bracket MUST be supported securely. Add fixture support carrier if wall will not 

provide adequate support. Anchor hanger securely to wall using all six (6) 1/4 in. dia. mounting 
holes.

IMPORTANT:

5-7/8 in. (150mm) dimension from wall to centerline of trap must be maintained for proper fit.

INSTALLATION OF COOLER

3) Hang the cooler on the hanger bracket. Be certain the hanger bracket is engaged properly in 

the slots on the cooler back as shown in FIGURE 3.

4) Remove the four (4) screws holding the lower front panel at the bottom of cooler. Remove the 

front panel by pulling straight down and set aside, SEE FIG. 4, FIG.5.

WATER CONNECTION TO THE MAIN

5) Before making the water connection, make sure the mains water pressure is between 20 and 

60 psi.

6) If the mains water pressure exceeds 60 psi, predispose a pressure reducer capable of reducing 

the latter to the 20~60 psi.

7)Connection to the mains water supply is carried out with the aid of  1/4in PE tube 

provided(dia 1/4").

8)The tube terminals (1/2”×1/4”fitting) must be connected to the mains supply by means of a 

“water supply valve” G (not provided). SEE FIGURE 3.

FILLING INTERNAL ICE BANK

9) Remove the white plugs  marked" Fill Ice Bank".
10) Connect water supply tube into the connector "Fill Ice Bank".
11)Open the "water supply valve" G, let the water enter the ice bank slowly and fill the ice bank; 

once reach the right level, the exceeding water will run over the outlet of Overflow pipe, then close 
"water supply valve" G. After that, connect water pipe into coupling-- "water in" with proper 
pressure. SEE FIGURE 3.

Note: 

The connection of tank charge--"Fill Ice Bank" has to be disconnected. 

12) Insert the white plug back to its original position(overflow).

DRAIN CONNECTION

The drain water is clean and it comes from the tray(basin) that collects any dripping during 
dispensing.
Connect the drain pipe (O.D. 20mm) to drain with a drain-trap. If necessary, cut the pipe so as to 
avoid narrowing or rising or backflow problems.

CLEANING

Warm, soapy water or mild household cleaning products can be used to clean the exterior panels 

of the TB35 water coolers.  Extra caution should be used to clean the mirror finished stainless steel 
panels.  They can be easily scratched and should only be cleaned with mild soap and water or 
Windex glass cleaner and a clean, soft cloth.  Use of harsh chemicals or petroleum based or abrasive 
cleaners 

will void the Warranty.

Summary of Contents for KM35 Series

Page 1: ...PROCEDURE THIS GROUNDING MAY BE IN THE BUILDING OR MAY OCCUR AWAY FROM THE BUILDING THIS GROUNDING CAN CAUSE ELECTRICAL FEEDBACK INTO A FOUNTAIN CREATING AN ELEC TROLYSIS WHICH CAUSES A METALLIC TASTE OR AN INCREASE IN THE METAL CONTENT OF THE WATER THIS CONDITION IS AVOIDABLE BY USING THE PROPER MATERIALS AS INDICATED ANY DRAIN FITTINGS PROVIDED BY THE INSTALLER SHOULD BE MADE OF PLASTIC TO ELECT...

Page 2: ...d Valve Switch Electrical Access Panel Drainage Funnel Orifice Fill Ice Bank Orifice Water Inlet Orifice Water Outlet Pushbar Side Upper Plastic Shroud Pushbar Front Basin Faucet Bubbler Lower Shroud Compressor Water Pipe Coupling Cold Water Thermostat Orifice Overflow Out Water Pipe Retaining Screw M5 Waste Water Pipe Bubbler Head Stream Adjuster Rubber Seal Locknut Non return Pad M10 Nut Horn Pa...

Page 3: ...Page 3 Rev A 6 2012 FIGURE 3 ...

Page 4: ... 2 1 4 fitting must be connected to the mains supply by means of a water supply valve G not provided SEE FIGURE 3 FILLING INTERNAL ICE BANK 9 Remove the white plugs marked Fill Ice Bank 10 Connect water supply tube into the connector Fill Ice Bank 11 Open the water supply valve G let the water enter the ice bank slowly and fill the ice bank once reach the right level the exceeding water will run o...

Page 5: ...it remove lower shroud disconnect drain remove four screws from tabs along lower edge of upper shroud unplug two wires and water tube SEE FIG 4 FIG 5 FIG 6 Bubbler To remove the bubbler first disconnect the power supply The underside of the bubbler can be reached through the access panel Item 8 on the underside of the upper shroud Item 14 Remove the access panel by removing the retaining screw ite...

Page 6: ... When installing replacement bubbler and pedestal tighten Nut only to hold parts snug in position Do Not Overtighten BUBBLER DETAIL 26 27 28 29 30 31 32 33 34 35 LOWER COVER SCREWS BASINASSEMBLY SCREWS SCREWS FIGURE 4 FIGURE 5 ...

Page 7: ... Rev A 6 2012 Switch Activation Closed Switch Detail Open Switch Detail Note Only side push activation is shown Front push works the same Page 7 ...

Reviews: