10
M.
Using a 3/8” spanner and 3/16” hex key, slacken off the
locking nut and adjust the grub screws so that the gate leaves
meet in the middle. Once centre position is correct, lock off grub
screw using nut.
L.
Using the 15/16” socket & ring spanner start to tighten the
bolt until the gate completely closes. (Note:- You may have to hold
the socket whilst using the ratchet). Once the gate is completely
closed tighten the locking nut to hold the tension.
Caution:- Continue to hold the ratchet firmly and do not release
until the lock nut is tightened. Now remove the socket and
spanner from the hinge. Repeat as necessary, to ensure that the
gate closes sufficiently, once opened and released.
Mounting double gates and tensioning spring
Caution! Over tensioning of the spring assembly will
result in failure of the product!!
N.
Ensure all nuts and grub screws (excluding adjustment screw)
on the gate are torqued to 39Nm. Finally, place black caps over
nuts. Ensure that the structure to which the gate is attached to
is sturdy, does not rotate and nuts and grub screws are torqued
as per manufacturers guidelines.
Note:- Installing Kee Gate
When installing Kee Gate on a pitched roof it is essential that the gate is mounted vertically level to the horizontal.
This can be accommodated by using standard 90 degree Elbows (15-8) (4No required per gate).
The elbows permit adjustment allowing the Kee Gate to be
orientated to the correct angle. If the gate is not set at the correct angle the hinge cannot be tensioned correctly
and the gate may not close as required.