KC-P30 x-series
Functions
Configuration manual V4.09
39
© KEBA
Amperage
Illustration
35 A
50 A
63 A
Information
Changes to the DIP switch settings only become effective after a restart of
the charging station!
To restart, press the "Service button" until the first signal tone sounds (ap-
prox. 1 second) or switch off the charging station for a short time via the
line circuit breaker.
Configuration for a charging network
For a charging network, the maximum permitted charging current per phase
and the maximum permitted charging capacity for the entire charging net-
work can be configured in the web interface (under Configuration > External
TCP Meter).
If the connection to the external meter gets interrupted, you can use the web
interface to configure the charging capacity at which charging is to continue.
If "0" is entered or if the field remains empty, the charging processes are in-
terrupted in the event that the connection to the external meter is interrupted.