Table 1. 

Boiler model 

K-2-70 

Nominal power (Q

N

) *

1

 

kW 

70 

Heated area 

class B buildings  *

2

 

m

2

 

602...1470 

class C buildings  *

2

 

322...770 

Fuel consumed

 

 

logs *

3

 

Size of logs L x Ø, up to 

cm 

L50 x Ø15 

Position of logs in furnace 

 

lengthwise or 

crosswise 

Fuel loading openings size: 

in front 

mm 

310 x 540 

on top 

mm 

310 x 540 

Furnace volume 

dm

(l) 

467 

Fuel charge combustion duration (Q

N

)  *

4

 

hrs 

Efficiency rate during operation at nominal power, no less than 

82 

Boiler class under  EN 303-5 

 

Boiler water capacity 

198 

Recommended min volume of accumulation vessel *

5

 

1260 

Water pressure in boiler, no more than 

bar (MPa) 

1,5 (0,15) 

Max permissible water temperature 

for opened heating system 

ºC 

95 

for closed heating system *

5

 

80 

Min return water temperature during operation 

ºC 

60 

Hydraulic resistance 

mbar 

8,5 

Operating ambient temperature 

ºC 

3 ... 40 

Temperature regulator adjustment range 

ºC 

65 ... 90 

Adapted cooling coil type *

6

 

 

AAG17 

Cold water used for excessive heat 
dissipation parameters: *

6

 (*

7

pressure  

bar 

≤ 0,2 

temperature 

ºC 

≥ 15 

Required smoke draught from the boiler 

no less than  

Pa 

35 

no more than  

40 

Exhausted flue temperature at nominal output, up to 

ºC 

203 

Exhausted flue quantity at nominal output 

kg/s 

0,058 

Connection sockets dimensions: 

flue channel 

mm 

Ø250 

heating system 

in 

G2-B 

drainage  

in 

G½ 

Overall dimensions (netto/brutto),  
not bigger than  

height 

mm 

1660 / 1863 

width 

mm 

  985 /   940 

length 

mm 

1675 / 1720 

Mass (netto/brutto), no more than (

10%) 

kg 

1041 / 1066 

*

1

 

Firing with 18 – 20 % damp birch firewood. It is not recommended to fire with firewood damper than 25 %. 

*

2

 

According  to  STR  2.01.02:2016  Energy  Performance  Projecting  And  Certification  Of  Buildings  requirements 

calculated amount of energy expressed for class B and C energy performance buildings. 

*

3

 

As alternative fuel may be used coal, lump wood waste, chip or peat briquettes. 

*

4

 

Fuel charge combustion duration depends on fuel type, moisture, outdoor temperature and other factors. 

*

5

 

It is not recommended in the opened heating system to mount boiler with accumulation tank. Intensive boiler stoking 

at 80 °C will cause the water inside of the boiler boiling, will appear the stranger noises. 

*

6

 

For the boiler with installed emergency cooling system

*

7

 

Available for installation having purchased separately (manufacturer UAB "Kalvis"). 

4.

 

Design description 

Note:  Since  boiler  construction  is  under  constant  improvement,  non-essential

 

deviations from this manual are possible. 

Summary of Contents for K-2-70

Page 1: ...CENTRAL HEATING SOLID FUEL BOILER KALVIS 2 70 TECHNICAL CERTIFICATE INSTALLATION AND MAINTENANCE MANUAL Made in Lithuania Pagaminta Lietuvoje LST EN 303 5 2012 20548 87 20548 93...

Page 2: ...e 12 7 1 System preparation for heating 13 7 2 Boiler start up firing 13 7 3 Air draught regulator adjustment 14 7 4 Boiler firing 14 7 5 Boiler extinguishing 15 7 6 Boiler cleaning 15 7 7 Frequently...

Page 3: ...a variety of solid lump well dried fuel If desired the boiler is easy to adapt for stoking in mechanized way with pellets The boiler is manufactured using modern materials and technologies We believe...

Page 4: ...oiler power is too high and it has to be operated at lower than nominal power we recommend to install the boiler with accumulation tank 5 Use fuel no damper than 25 In the case of higher fuel dampness...

Page 5: ...than 40 Exhausted flue temperature at nominal output up to C 203 Exhausted flue quantity at nominal output kg s 0 058 Connection sockets dimensions flue channel mm 250 heating system in G2 B drainage...

Page 6: ...er front has air draught regulator 17 controlling the primary air supply valve 2 thermometer 16 pressure gauge 18 hearth service door 1 covering inner cast iron door 3 Fuel loading chamber is closed b...

Page 7: ...ntry In the extreme case wooden pallet can be used as fuel for the boiler Picture 2 Boiler packing for transportation 6 Boiler installation Boiler is to be installed in the premises meeting the releva...

Page 8: ...h extra elbow its cross section cannot be less than the cross section of fume escape from boiler hole with bending radius no less than 100 mm tube between the boiler flue and chimney shall be no longe...

Page 9: ...firemen make the openings in the chimney joint in a suitable place for periodical cleaning of soot once a month it is recommended to have boiler examined by qualified chimney expert once a year Notice...

Page 10: ...rming which ensures the long service life of the boiler not allows to form the condensate There are not shown the auxiliary technological equipment of the boiler house expansion vessel valves and othe...

Page 11: ...ary air supply dampers 27 see also chapter 7 3 6 5 Connection of the boiler cooling system According to the requirements of LST EN 303 5 standard par 4 1 5 11 3 for boiler operation it is necessary to...

Page 12: ...oling system Attention Emergency cooling coil cannot be used for hot water preparation 7 Boiler operate Boiler can be operated by adult persons well familiarized with boiler construction and this tech...

Page 13: ...ng the boiler from the system are not closed 7 2 Boiler start up firing Before starting the boiler open the smoke draught damper 15 see picture 1 ignition damper 13 through the doors 1 and 3 put crush...

Page 14: ...and add more fuel in the hearth Tightly close fuel loading door 6 and ignition damper 13 According to the selected temperature with the means of air draught adjuster 17 open the primary air supply va...

Page 15: ...ically aggressive acids under effect of which boiler service life can be reduced significantly In order to make sure that the boiler is tight stock it at high intensity for several hours then stop sto...

Page 16: ...oving fuel out of the boilers burning chamber put burning fuel to the utensil with water to get as little fume as possible accessing the premises open windows and doors Do not pour water into burning...

Page 17: ...is uninstalled due to other reasons Boiler is constructed from various materials so Bring electric appliances if present to electric appliances recycling organization Metal parts go to metal scrap Rem...

Page 18: ...moisture 35 40 Just cut tree contains 35 60 water Tree cut in the beginning of winter contains least quantity of water Hardwood contains less water Wood has to be cut and split to make firewood Firewo...

Page 19: ...or free Manufacturer takes no obligation for boiler operation and related consequences grants no warrant if the boiler is inadequately selected poorly installed see chapter 6 or operated see chapter 7...

Page 20: ...ress Telephone In the case of failure please call Company Address Telephone Manufacturer UAB Kalvis Pramon s 15 LT 78137 iauliai Lietuva Lithuania Telephone 370 671 88891 E mail prekyba kalvis lt Warr...

Page 21: ...nsions Diameter Height Length Chimney draught Number of elbows Last revision date Outgoing smoke temperature Brief description of boiler connection Fuel used for testing Type During boiler testing fun...

Page 22: ...ddress Experts Telephone Failure works carried out Repairs date Expert s signature Company Address Expert Telephone Failure works carried out Repairs date Expert s signature Company Address Expert Tel...

Page 23: ...manual requirements Regarding that I have claims for this product __________________________________________ I think that my upper listed deficiencies are defects of your product so please send your r...

Page 24: ...24 Stick product barcode here...

Reviews: