Johnson Controls JRC Series Installation Operation & Maintenance Download Page 31

JRC-Series

R e v. :   D e c e m b e r   8 ,   2 0 2 1

T H E   S M A R T   S O L U T I O N   F O R   E N E R G Y   E F F I C I E N C Y

I n s t a l l a t i o n ,   O p e r a t i o n ,   M a i n t e n a n c e

31

Piping System Cleaning and Flushing

Piping System Cleaning and Flushing -

 Cleaning and 

flushing the WLHP piping system is the single most 

important step to ensure proper start-up and continued 

efficient operation of the system.
Follow the instructions below to properly clean and flush 

the system:

1.  Ensure that electrical power to the unit is disconnected.

2.  Install the system with the supply hose connected 

directly to the return riser valve. Use a single length of 

flexible hose.

3.  Open all air vents. Fill the system with water. DO 

NOT allow system to overflow. Bleed all air from the 

system. Pressurize and check the system for leaks 

and repair as appropriate.

4. 

Verify that all strainers are in place (the manufacturer 

recommends a strainer with a #20 stainless steel 

wire mesh). Start the pumps, and systematically 

check each vent to ensure that all air is bled from the 

system.

5.  Verify that make-up water is available. Adjust make-

up water as required to replace the air which was 

bled from the system. Check and adjust the water/air 

level in the expansion tank.

6.  Set the boiler to raise the loop temperature to 

approximately 86°F [30°C]. Open a drain at the 

lowest point in the system. Adjust the make-up water 

replacement rate to equal the rate of bleed.

7. 

Refill the system and add trisodium phosphate in 

a proportion of approximately one pound per 150 

gallons [1/2 kg per 750 l] of water (or other equivalent 

approved cleaning agent). Reset the boiler to raise 

the loop temperature to 100°F [38°C]. Circulate the 

solution for a minimum of 8 to 24 hours. At the end of 

this period, shut off the circulating pump and drain the 

solution. Repeat system cleaning if desired.

8.  When the cleaning process is complete, remove the 

short-circuited hoses. Reconnect the hoses to the 

proper supply, and return the connections to each of 

the units. Refill the system and bleed off all air.

9.  Test the system pH with litmus paper. The system 

water should be in the range of pH 6.0 - 8.5 (see 

table 3). Add chemicals, as appropriate to maintain 

neutral pH levels.

10. 

When the system is successfully cleaned, flushed,    

refilled and bled, check the main system panels, 

safety cutouts and alarms. Set the controls to properly 

maintain loop temperatures.

DO NOT use “Stop Leak” or similar chemical agent in 

this system. Addition of chemicals of this type to the 

loop water will foul the heat exchanger and inhibit unit 

operation.

CAUTION! 

To avoid possible damage to a plastic (PVC) piping 

system, do not allow temperatures to exceed 110ºF (43ºC).

Note: The manufacturer strongly recommends all piping 

connections, both internal and external to the unit, be 

pressure tested by an appropriate method prior to any 

finishing of the interior space or before access to all 

connections is limited. Test pressure may not exceed 

the maximum allowable pressure for the unit and all 

components within the water system. The manufacturer 

will not be responsible or liable for damages from water 

leaks due to inadequate or lack of a pressurized leak 

test, or damages caused by exceeding the maximum 

pressure rating during installation. 

 

CAUTION!

 

Summary of Contents for JRC Series

Page 1: ...ter Source Heat Pumps Installation Operation Maintenance Supersedes 14805 NOM1 0521 Form 14805 NOM1 1221 97B0035N10 Issue Date December 8 2021 JRC Series Water Source Heat Pump MODELS JRC 0 75 1 5 Ton...

Page 2: ...ons 13 Ground Water Heat Pump Applications 14 Water Quality Standards 16 Electrical Line Voltage 20 Electrical 21 JRC Series Wiring Diagram Matrix 24 CXM Controls 25 DXM Controls 26 Safety Features CX...

Page 3: ...Model Type Unit Size None Motorized Water Valve Autoflow 2 25 Gpm Ton Autoflow 3 0 Gpm Ton Motorized Water Valve Afr 2 25 Motorized Water Valve Afr 3 0 Secondary Circulation Pump Water Circuit Options...

Page 4: ...ce with the regulations of ALL authorities having jurisdiction and MUST conform to all applicable codes It is the responsibility of the installing contractor to determine and comply with ALL applicabl...

Page 5: ...he system components Remove any dirt or debris found in or on these components Pre Installation Installation Operation and Maintenance instructions are provided with each unit Horizontal equipment is...

Page 6: ...ze Bottom Return in mm 1 10 x 30 x 1 254 x 762 x 25 1 10 x 36 x 1 254 x 914 x 25 Front Return In mm 1 7 x 29 5 x 1 8 178 x 749 x 3 2 1 7 x 35 5 x 1 8 178 x 902 x 3 2 Unit Size Bottom Return Std 5 Base...

Page 7: ...ecure the subbase in place 6 Remove subbase shipping support bracket and discard 7 Make all necessary electrical connections as described in the Electrical Wiring section of this manual Consult the wi...

Page 8: ...tly Horizontal runs of condensate hose should be pitched downward 1 4 inch minimum for every foot 10 mm per 46 cm of hose Avoid low points because dirt collects in these areas and may cause blockage I...

Page 9: ...tional Motorized Water Valve 1 75 44 Out In Water Connections 1 2 FPT 2 25 57 In Out 11 25 286 2 00 51 1 50 38 8 00 Min 203 2 25 57 5 8 15 9 ID Vinyl Hose 8 00 Min 203 Water Connections 1 2 FPT 11 25...

Page 10: ...D Vinyl Hose Optional Motorized Water Valve Optional Autoflow Valve Water Connections 5 8 15 9 OD Copper 1 2 FPT or 1 2 MPT Optional isconnect Box unted to cabinet not chassis Optional Motorized Water...

Page 11: ...e or pipe joint compound that is applied Maximum allowable torque for brass fittings is 30 ft lbs 41 N m If a torque wrench is not available tighten finger tight plus one quarter turn Tighten steel fi...

Page 12: ...enoid valve for use in variable speed pumping systems may also be included in the hose kit The piping system should be flushed to remove dirt piping chips and other foreign material prior to operation...

Page 13: ...to assist the contractor in installing trouble free ground loops These instructions are recommendations only State provincial and local codes MUST be followed and installation MUST conform to ALL app...

Page 14: ...the pH 7 5 and the calcium hardness is less than 100 ppm scaling potential is low If this method yields numbers out of range of those listed the Ryznar Stability and WARNING Polyolester Oil commonly...

Page 15: ...re is constantly varying two pressure gauges may be needed Adjust the valve until the desired flow of 1 5 to 2 gpm per ton 2 0 to 2 6 l m per kW is achieved A second method of flow control requires a...

Page 16: ...l l e c a i r e t c a B Sulfate reducing 0 0 0 0 L m s l l e c a i r e t c a b Suspended Solids 0 1 0 1 0 1 0 1 m p p S S T Earth Ground Resistance 0 s m h O Consult NEC local electrical codes for gro...

Page 17: ...ed 7 If water temperature is expected to fall below 40 F antifreeze is required Refer to the heat pump IOM for the correct solution ratios to prevent freezing Hydrogen Sulfide has an odor of rotten eg...

Page 18: ...esistance measured should be zero Ohms The NEC allows a resistance to ground up to 20 Ohms Any resistance above zero indicates a poor earth ground which may be the result of a hot neutral line or that...

Page 19: ...If higher than 500mV electrolysis will occur and corrosion will result If voltage is measured the cause is a high resistance earth ground or current on the neutral conductor Remedial measures should...

Page 20: ...open the power supply disconnect switch and secure it in an open position during installation CAUTION Use only copper conductors for field installed electrical wiring Unit terminals are not designed...

Page 21: ...0 5 N A 4 20 5 13 15 0 8 5 00 5 93 15 E 265 60 1 239 292 3 5 22 0 0 4 N A 3 90 4 78 15 0 7 4 60 5 48 15 JRC12 A 115 60 1 104 126 9 5 50 0 1 0 N A 10 50 12 88 20 1 4 11 90 14 28 20 G 208 230 60 1 197 2...

Page 22: ...ld supplied and field installed B only required with systems employing remote mounted thermostats Figure 3 Typical Field Installed Wiring WARNING To avoid possible injury or death due to electrical sh...

Page 23: ...e 18 AWG wire Wire the appropriate thermostat as shown in Figure 7 to the low voltage terminal strip on the CXM or DXM control board Practically any heat pump thermostat will work with JRC WSHP units...

Page 24: ...ard JRC DIGIT 8 L N CXM w MPC JRC DIGIT 8 M P DXM w MPC JRC DIGIT 8 D S DXM Standard S1 S1 S1 S1 S2 S2 1 2 3 4 5 OFF ON 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 1 2 3 4 5 OFF ON OFF ON OFF ON O...

Page 25: ...ted to R Clipped AL2 dry contact no connection DIP Switches Note In the following field configuration options DIP switches should only be changed when power is removed from the CXM control DIP switch...

Page 26: ...e control is attempting a retry of a fault the status LED will slow flash slow flash one flash every 2 seconds to indicate the control is in the process of retrying Field Configuration Options Note In...

Page 27: ...able 7c Accessory DIP Switch Settings 1 3 Thermostat type heat pump or heat cool DIP 1 3 provides selection of thermostat type Heat pump or heat cool thermostats can be selected When in heat cool mode...

Page 28: ...he compressor contactor coil The high pressure fault recognition is immediate does not delay for 30 continuous seconds before de energizing the compressor High pressure lockout code 2 Example 2 quick...

Page 29: ...mode and the LT2 sensor is colder than the LT1 sensor Swapped LT1 LT2 thermistor code 9 ESD DXM only The ESD Emergency Shut Down mode can be enabled from an external common signal to termi nal ESD to...

Page 30: ...30 120 1 49 20 90 6 7 32 Requires optional insulation package when operating below the dew point Requires antifreeze optional insulation package and jumper clipped UNIT OPERATING LIMITS All JRC Model...

Page 31: ...f water or other equivalent approved cleaning agent Reset the boiler to raise the loop temperature to 100 F 38 C Circulate the solution for a minimum of 8 to 24 hours At the end of this period shut of...

Page 32: ...promotes longevity of hoses and fittings see Table 3 System flushing Verify that all hoses are connected end to end when flushing to insure that debris bypasses the unit heat exchanger water valves an...

Page 33: ...urn thermostat to OFF position A hissing noise indicates proper functioning of the reversing valve 6 Allow five 5 minutes between tests for pressure to equalize before beginning heating test a Adjust...

Page 34: ...57 8 13 8 13 8 13 9 14 8 13 7 12 16 18 12 14 8 10 18 24 18 24 18 24 164 174 165 175 167 177 372 392 375 395 379 399 17 22 18 23 19 24 13 18 13 18 13 18 14 5 16 5 11 2 13 2 7 9 9 9 35 41 35 41 36 42 11...

Page 35: ...9 14 9 14 9 14 11 16 9 14 6 11 15 8 17 8 14 9 16 9 14 16 18 24 18 24 18 24 164 174 165 175 167 177 372 392 375 395 379 399 17 22 18 23 19 24 13 18 13 18 13 18 14 5 16 5 11 2 13 2 7 9 9 9 35 41 35 41 3...

Page 36: ...and data entries before the system is put into full operation Temperatures F or C Antifreeze __________________ Pressures PSIG or kPa Type __________________ Cooling Mode Heating Mode Return Air Tempe...

Page 37: ...erating conditions and be replaced when necessary Units should never be operated without a filter Washable high efficiency electrostatic filters when dirty can exhibit a very high pressure drop for th...

Page 38: ...e of unit toward outlet Poor venting Check vent location X Moisture on sensor Check for moisture shorting to air coil X X Plugged air filter Replace air filter x X Restricted Return Air Flow Find and...

Page 39: ...ck fan motor operation and air flow restrictions Too high of external static Check static vs blower table X Reduced or no water flow in cooling Check pump operation or valve operation setting Check wa...

Page 40: ...HWG HEATING CYCLE ANALYSIS PSI SAT PSI SAT F F AIR COIL F F FP2 HEATING LIQUID LINE F EXPANSION VALVE AIR COIL F F PSI SAT PSI SAT F F F F WATER IN WATER OUT PSI PSI F F WATER IN WATER OUT PSI PSI Use...

Page 41: ...JRC Series Rev Decem b er 8 2021 TH E SMART SOLUTION FOR ENERGY EFFICI E N CY Installation Operation Maintenance 41 Notes...

Page 42: ...WATE R SOURCE HEAT PUMPS JRC Series Rev Decemb er 8 2021 Installation Operation Maintenance 42 Notes...

Page 43: ...JRC Series Rev Decem b er 8 2021 TH E SMART SOLUTION FOR ENERGY EFFICI E N CY Installation Operation Maintenance 43 Notes...

Page 44: ...o Subordinate 08 19 20 Created Johnson Controls works continually to improve its products As a result the design and specifications of each product at the time for order may be changed without notice...

Reviews: