TABLE OF CONTENTS
MOUNTING INSTRUCTIONS
8.
Install hydraulic tank.
Slide hydraulic tank back into position. Tighten front 1/2”
carriage bolt and hardware (X). Install and tighten rear 1/2” hardware (V). Lift rear
tank mount into position and secure to right rear mounting bracket and
crossframe with 3/4” hardware (Z). Torque nuts to 200-240 ft-lbs. Install rear and
tighten front 5/16” fender wall hardware (U). Reinstall fender with four 5/16”
crews and hardware (S). Install clamps securing 2” pump suction line.
9.
Install fuel tank.
Move fuel tank back
into position. Install two 1/2” carriage
bolts and hardware (L) from frame to
fuel tank and fender wall. Lift rear tank
mount into position and secure to left
rear mounting bracket and crossframe
with 3/4” hardware. Torque nuts to 200-
240 ft-lbs. Install 5/16” hardware (M)
securing fender wall to tank mount.
Reconnect wires to fuel sender (J) and
fuel lines to tank. Install fender with four
5/16” screws and hardware (H).
10.
Install front mounting bracket.
Bolt the front mounting
bracket (13) over the front lip of the foot platform using the
3/4” bolts (14) and corresponding hardware. Find the two
1/2” nuts welded onto the left and right sides of the bracket.
Mark the hole locations on the side lips of the foot platform
and remove the front bracket. Drill two 9/16” holes through
the lip of the foot platform at the marked locations. Loosely
bolt the front bracket to the machine using 1/2” X 1 1/2”
bolts (15) and lock washers on the right hand side under
the platform. Use 1/2” X 2” bolts and lockwashers on left
hand side under platform. Insert a rubber isolator (16) in
the mounting bracket isolator cups.