SPECIFICATIONS
Voltages 575, 460, 380, 230, 220, 208V, 3 ph, 60Hz
415, 380, 220, 115, 42V, 3 ph, 50Hz
Power
5 hp
3729 W
Capacity
750 / hour
Control Handles
Electric Dual Anti--tie Down
12V
Brake
Electric or Mechanical
Blade Diameter
16 in
406 mm
18 in
457 mm
21 in
533 mm
Blade Speed
1400 RPM
Cutting Depth (max.)
5.1 in
130 mm
6.1 in
155 mm
7.6 in
193 mm
Overall Length
37 in
940 mm
Weight (Electronic Brake)
110 lbs
49.9 kg
(Mechanical Brake)
130 lbs
59 kg
Vibration
less than (<) 120 dB
<
1.0 m/sec
2
Noise
85 dB
INSTALLATION INSTRUCTIONS
ALWAYS DISCONNECT THE POWER SUPPLY IN ACCOR-
DANCE WITH OSHA’S LOCKOUT/TAGOUT PROCEDURES
(29CFR 1910.147) BEFORE PERFORMING ANY REPAIRS OR
MAINTENANCE.
ALL WIRING MUST BE DONE IN ACCORDANCE WITH NA-
TIONAL, STATE AND LOCAL ELECTRICAL CODES.
1 Install the electrical control box in a convenient
location.
2 Wire the electrical control box.
Note:
Electrical
control boxes are different for different power sup-
plies. You must have the proper control box for your
power supply. Refer to Tables 1 and 2 for applicable
control box numbers.
2.1 Attach terminals L1, L2, and L3, and earth
ground to the applicable power supply.
See wir-
ing diagram inside control box cover.
2.2 The connection between the SEC 400 and the
electrical control box is pre--wired and is
approximately 20 feet long. Tighten the com-
pression nut on the female connector to ensure
proper sealing.
Refer to Figure 1.
3 Install a balancer above the work station on a trolley.
3.1 The trolley should have sufficient travel to allow
the operator to reach the entire work area.
Figure 1
Power Supply
4 Suspend the SEC 400 from the balancer.
4.1 Adjust the balancer to the operator’s preference.
OPERATION INSTRUCTIONS
1 Turn on the power.
2
Each day,
before you begin operation, go through
the following checklist:
2.1 Make sure that the SEC 400 moves freely on its
balancer.
2.2 Make sure that the dual anti--tie down control
handles (the front and the rear handles) are
working correctly.
Depress
one trigger, then
pause one second and depress the other trigger
and the tool should not start. Repeat this proce-
dure reversing the triggers.
Depress
both trig-
gers simultaneously (within one half second of
each other) and the tool should start. With the
tool running,
release
one trigger and the tool
should stop within 1.5 seconds.
Continue
hold-
ing the depressed trigger and then depress the
other trigger. The tool should not start. Repeat
this procedure holding the other trigger.
If the
tool malfunctions, remove it from service and re-
port the problem to your supervisor immediate-
ly.
2.3 Make sure that the brake is working correctly.
Depress
both triggers simultaneously to start
the saw.
Release
either trigger and the saw blade
should stop within 1.5 seconds.
If the tool mal-
functions, remove it from service and report the
problem to your supervisor immediately
.
Always use two hands when starting and stopping the
tool. Continue holding the tool with two hands until the
saw blade comes to a complete stop.