8.-INSTALLATION OF MODULAR EQUIPMENTS ON TOP OF BINS 

Modular ice makers should be installed on top of bins, following the instructions contained in this manual. 
The resistance and stability of the container-machine/s assembly should be verified, as well as the fastening elements. Follow bin manufacturer instructions. 

 

 

 

FACTORY SETTINGS

 

 

Head pressure regulator: 10 bar. 

 

Pressure switch protection: 30 bar. 

 

 
Start-Up 

1.- Previous Checkup  

a)

 

Is the machine leveled?  

b)

 

Voltage and frequency are the same as those on the nameplate? 

c)

 

Are the discharges connected and operating?  

d)

 

Will the ambient temperature and water temperature remain in the following range? 

  

ROOM 

WATER 

MAXIMUM 

109º F  / 43º C    

95º F  / 35ºC     

MINIMUM 

41º F  / 5º C    

41º F  / 5ºC    

e)

 

Is water pressure appropriate?  

MINIMUM 

14 psig (1 Bar)  

MAXIMUM 

85 psig (6 Bar) 

 

NOTE: In case input water pressure is higher than 85 psi (6 bar), install a pressure regulator. 

 
 
 
 
For undercounter machines:  

Summary of Contents for SPIKA NG 130

Page 1: ...AKERS UNDERCOUNTER MODELS MÁQUINAS DE HIELO EN CUBITOS MODELOS COMPACTOS MACHINES A GLAÇONS MODELES COMPACTES SPIKA NG 130 SPIKA NG 160 SPIKA NG 230 SPIKA NG 360 ICE CUBE MAKERS MODULAR MODELS MÁQUINAS DE HIELO EN CUBITOS MODELOS MODULARES MACHINES A GLAÇONS MODELES MODULAIRES SPIKA MS 500 SPIKA MS 600 SPIKA MS 1000 ...

Page 2: ...NANCE AND CLEANING PROCEDURES 11 USER TROUBLESHOOTING GUIDE 17 WIRING DIAGRAMS 19 Introduction Thank you for purchasing a Spika Series Ice Cube Maker by ITV You have purchased one of the most reliable ice making products on the market today Carefully read the instructions contained in this manual since they provide important information relative to safety during installation use and maintenance ...

Page 3: ... To see Installation chapter 7 In order to assure the proper operation and efficiency of this equipment it is extremely important to follow the recommendations of the manufacturer especially those related to cleaning and maintenance operations which should be performed by qualified personnel only CAUTION The intervention of non qualified personnel besides of being dangerous could result in serious...

Page 4: ...nt grille In case the front grille is either total or partially obstructed or due to its placement it receives hot air from another device we recommend in case it is not possible to change the location to install a water cooled machine The air cooled SPIKA MS modular ice makers take the air through the back section and drive it off through the two lateral louvers In the case it is not possible to ...

Page 5: ... you can see below are recommended for efficient operation and servicing UNDERCOUNTER MODELS MODULAR MODELS 4 CONNECTION DIAGRAMS The location must allow enough clearance for water drain and electrical connections in the rear of the ice machine UNDERCOUNTER MODELS ...

Page 6: ...onvenient that the drainage pipe is 1 18 30 mm inside diameter and with a minimum gradient of 0 36 ft 3 cm meter see figure CORRECT INCORRECT INCORRECT 7 ELECTRICAL CONNECTION IT IS MANDATORY TO GROUND THE EQUIPMENT To avoid possible discharges on individuals or damages to the equipment the machine should be grounded following local and or national regulations as needed THE MANUFACTURER SHALL BE H...

Page 7: ...TINGS Head pressure regulator 10 bar Pressure switch protection 30 bar Start Up 1 Previous Checkup a Is the machine leveled b Voltage and frequency are the same as those on the nameplate c Are the discharges connected and operating d Will the ambient temperature and water temperature remain in the following range ROOM WATER MAXIMUM 109º F 43º C 95º F 35ºC MINIMUM 41º F 5º C 41º F 5ºC e Is water pr...

Page 8: ...eds 85ºF 29 5ºC or water inlet temperature exceeds 68ºF 20ºC the following adjustments should be made to ensure a proper efficiency Control Schematics Considering the fabrication time and water inlet time you can make the switches adjustments accordingly ...

Page 9: ...es from the water tray to the upper distributor flowing through each cube cell where it freezes 7 Harvest sequence The hot gas valve is opened during a certain time programmed with the switches configuration from the previous table and at the same time energizes the water inlet valve during a certain time to fill the water tray with the appropriate quantity of water The ice slab slides off the eva...

Page 10: ...t 10 Mix enough cleaning solution as in point 5 to clean parts and interior food zone surfaces 11 Remove shield 12 Clean all surfaces of the shield with the cleaner solution using a brush not a wire brush or cloth Rinse all areas with water 13 Clean all the interior surfaces of the freezing compartment including storage bin with the cleaner solution using a brush or cloth Rinse all areas with wate...

Page 11: ...3 Use the sanitizer water solution to sanitize all surfaces of the bin Use a nylon brush or cloth 4 Rinse with plenty of water dry run the machine and open water faucet CLEANING THE CONDENSER 1 Air Condenser 1 Disconnect machine and close water faucet 2 For undercounter models remove the front grid by pressing the two clips placed at right side see figure 3 Clean condenser using a vacuum cleaner s...

Page 12: ...r valve blocked Check an clean Bin full and ice touching thermostat tube but machine doesn t stop Bin thermostat doesn t open only operates at harvest time Adjust thermostat electric box under top cover Ice slab empty or too thick Disadjusted cycle time Adjust thermostat electric box under top cover Difficult to release ice slab at harvest Unit bad leveled tilted to back Level down front Not enoug...

Page 13: ......

Reviews: