30
Step 4: Check other content
After completing the above check before starting, the following items need to be carefully
checked to ensure that they are correct.
All links are made in accordance with Chapter 6 of this manual.
The protective shield inside the equipment has been firmly installed.
The emergency shutdown button is released.
The AC side and DC side circuit breakers have been disconnected, i.e. they are in
the "OFF" position.
The multimeter is used to detect whether the AC and DC side voltages meet the
starting conditions of the inverter, and there is no danger of overvoltage.
The door of the cabinet has been closed and the key of the cabinet door has been
pulled out and handed over to a special person for safekeeping.
For the long downtime energy storage inverter, before starting, the equipment must be
thoroughly and meticulously checked to ensure that all indicators meet the requirements
before starting.
7.2 Start-Up Operation Flow
After all of the above are satisfied, the energy storage inverter can be turned on. The
operation steps are as follows:
Step 1:
Make sure that the DC side and AC side are connected correctly and the DC side
voltage is lower than 850V.
Step 2:
Close AC and DC circuit breaker switches;
Step 3:
Close lightning protection switch KB4, auxiliary power switch KB1, contactor power
switch KB2, (and off-grid integrated model needs to close KB3);
Step 4:
After completing the above steps, through the switch menu on the touch screen,
click on the inverter to open. After the machine is booted normally, it can see the running
state of the machine through the touch screen.
Step 5:
After the machine is running normally, close the cabinet door and hand over the key
to a special person for safekeeping.
WARNING