Pre-installation preparation
Mechanical installation
Electrical installation
Installation Completion Check
Trial run test
Start
End
5
Mechanical Installation Guidance
5.1 Precautions Before Installation
Installation of this series of energy storage inverters requires simultaneous operation
of at least two qualified personnel, and all electrical installations must conform to local
electrical installation standards.
When installing, do not touch other parts of the cabinet except the terminal.
Safety signs must be set up at all upstream isolators to prevent closing during
construction.
5.2 Installation Process
The installation process of BD 30-150kW-P energy storage inverters is as follows: