background image

ITABAR Flow Sensor  Type  

IBF 

 Operating 

Manual 

 

8. Measurement 

Start-Up 

Make sure that: 
-  all installation openings are closed  

 

      (sensor end support IBF-21 / 26 / 36 / 66). 
-  all installed parts are securely bolted together. 
-  all instrument valves are closed. 
Now the pipe can be cleared for the appropriate 
medium 
Check all connections, especially the flanges 
Then open the instrument valves to the 

p-transmitter. 

 

9.  Preventive Maintenance of the ITABAR-
 Sensors 

ITABAR sensors are insensitive to dirt and soil 
build-up and therefore nearly maintenance-free. 

 

10. Trouble 

shooting 

If, after the start-up of the ITABAR sensor, any 
measuring errors occur, they may possibly be 
corrected quite easily: 

 

error: 

 

No differential pressure indication. 

 

Correction: 

 

Check whether all instrument valves to the 

transmitter are opened. 
Check the alignment of the sensor with the pipe. The 
arrow on the sensor must point exactly in the flow 
direction (downstream). 

 

Note: 

 

With highly corrosive media it is possible (if the 
sensor material has been specifically selected for 
such operating conditions) that a connection 
between the plus and minus sides has been formed. 
This can only be checked after removal of the sensor 
from the pipe. Close the holes in the sensor rod and 
blow through both minus and plus connections of 
the sensor (e.G. with pressurized air). If air emerges 
from the opposite connection, the sensor is 
defective. In this case, please notify the 
manufacturer. 

 

Summary of Contents for Itabar IBF

Page 1: ...Installation of the ITABAR Sensor 6 7 Installation of the Attachments and the Dp transmitter 8 8 Measurement Start Up 9 9 Preventive Maintenance 9 10 Trouble Shooting 9 INTRA AUTOMATION GmbH Me und R...

Page 2: ...ns ITABAR Flow sensors type IBF can be used under the following conditions Operating pressure max 320 bar Operating temperature 50 C to 1000 C Nominal Pipe Diameters DN 40 to DN 12000 The sensor mater...

Page 3: ...low measurements of liquids the ITABAR sensor must be installed in the lower half of the pipe circumference the connections to the instruments have to be located below the pipe axis This way gas or ai...

Page 4: ...hysical principles Its design incorporates no moving parts which are subject to wear Fig 6 The sensor is not affected by being slightly out of alignment The influence on the accuracy of the measuremen...

Page 5: ...ion of the most advantageous installation location As a general rule regulating valves throttle valves and gate type valves should be installed behind the sensor NOTE If the recommended straight pipe...

Page 6: ...flow direction Tighten the bolts and nuts Note On flanges with eight bolt holes the welding stud must be welded on so that the bolt holes in the flange form an angle of 22 5 with the pipe axis see Fi...

Page 7: ...m diameter into the pipe The subsequent Stepps correspond to the installation of the ITABAR sensor type IBF 21 Oberserve the H dimension during the welding see also Fig 9 6 7 Installation of Type IBF...

Page 8: ...pressure transmitter should always be installed above the ITABAR sensor in order to avoid measurement degradation due to condensation and presence of solid particles see Fig 14 Fig 14 7 3 ITABAR senso...

Page 9: ...ng errors occur they may possibly be corrected quite easily error No differential pressure indication Correction Check whether all instrument valves to the p transmitter are opened Check the alignment...

Reviews: