LSU220A : Load Support Unit
Operators Manual
To get the unit into calibration adjustment mode press the START push
button and the OUTPUT TRIM
q
push button both at the same time.
Then release the push buttons.
The GREEN RUN LED should then flash at a steady rate.
By using the OUTPUT TRIM
pq
push buttons adjust the displayed current
so that it matches as near as possible the current measured on the
calibrated ammeter connected to the output terminals. Note if you press
and hold either the
pq
push buttons the adjustment will be continuous.
Once complete press the START push button once and verify that it stops
flashing and remains steady.
Press the STOP push button.
Calibration current adjustment is complete.