3.Receiving and Installation
ED. 2010/11
3.
Receiving and Installation
3.1.
CHECK THE SHIPMENT
The first thing to do on receiving the valve is to verify that it is matches the delivery note.
INOXPA will inspect all the equipment before packing, although it cannot guarantee that the merchandise will arrive intact to
the user. For this reason, the valve received and any other article should be checked and, if it is found not to be in good
condition and/or not all parts are included, the carrier should submit a report as soon as possible.
Each valve has a manufacturing number engraved. Indicate the manufacturing number in all documents and correspondence.
3.2.
DELIVERY AND UNPACKING
INOXPA will not be responsible for the inappropriate unpacking of the valve and its components.
3.2.1.
Delivery:
Check that all the parts indicated in the delivery slip exist
Complete valve.
Its components (if supplied).
Delivery slip.
Instruction manual.
3.2.2.
Unpacking:
Remove all traces of packing materials from the valve or parts.
Inspect the valve or its constituent parts for possible damage caused during transport.
Avoid any possible damage to the valve and its components.
3.3.