28
Transportation, Installation, Commissioning
LL1602.10043 - 04.08.2014
ABC
COmmISSIONING
Attaching the filler/breather filter
See also "Important information before commissioning" manual.
Bleeding the Hydraulic System
refer to the chapter "Service and Maintenance".
Loss of data after a longer idle period
The machine is only fully operable only after complete data input.
When the machine has not been in use for a long period of time the data in the
RAM can be lost.
In such a case the data must be entered again before starting up the machine.
The data are saved in the commissioning sheet and stored on a memory device.
The commissioning sheet and the memory device are stored in the document box
on the control cabinet door.
Switching-on the Machine
See chapter "Setting-up and Operation basics".
Always charge the coolant tank before switching on the coolant
pump.
A dry running coolant pump will get damaged.