3.30 COMMISSIONING BOILER CHECK 

LIST.

A  suggested method of commissioning the 

boiler, actual method can very according to the 

boiler make type and the installation. The boiler 

must always be installed, and commissioned 

by an qualified gas technician. The installer 

certifies that this Boiler has been installed to 

the manufacturer’s instructions, has been filled, 

commissioned and is ready for use.

No.

Description

when done

1

Read carefully the instruction manuals supplied with this boiler.

2

BEFORE INSTALLING THIS BOILER FLUSH OUT THE PIPES UNTIL CLEAN WATER IS ACHIEVED. IF REPLACING 

AN OLD BOILER, HUNT HEATING RECOMMENDS A POWER FLUSH

3

Turn off all service to this boiler - water, gas and power. Install the boiler as shown in the instructions following and 

connect all services.

4

Turn on water to fill system, check for leaks regularly and bleed air from all points.

Bleed the air from all the pumps in the system, and rotate the impeller shaft.

5

Check that all radiators valves are open, all lock shields remove the thermostatic valve heads, fully open.

6

Turn ON gas, bleed air out at the isolation valve union. Reseal and check for gas leaks.

7

Turn electricity on at the power point. At the boiler front panel set the temperature setting to the lowest setting, switch 

boiler to ON position.

The “Power on” Indicator should light. Turn the boiler off at the front panel.

8

Turn the room thermostat to the manual ON position set the temperature to a high level so that it does not switch off 

during the commissioning phase. The thermostat will unusually click and shows an Indicator in the window.

9

Boiler should start fan, pump and ignite gas. If it fails first few times this may be just residual air in the gas line. A noisy 

water pump indicates there is air in the water pipes.

10

Boiler lights and heats the water. Check gas flame is the correct colour and for gas and water leaks as the system heats up.

11

Check that heat is circulating to all radiators through the manual or thermostatic radiator valve located on the flow pipe 

(unless reverse flow thermostatic valves).

12

Allow the boiler to heat up to the set temperature and switch off. Re-adjust the boiler temperature to a mid temperature point. 

CAUTION, if this is connected to a floor heating system. The boiler should re light and increase the water temperature 

to the new setting.

13

Check that all radiators are hot all the way up. If the radiator is cold at the top, then there is usually air in the radiator 

Bleed the radiator. Balance the system so that all radiators are hot as according to the radiator installation manual. Adjust 

the boiler water temperature.

14

Set the room thermostat to the correct times and temperatures according to the manufacturer’s instructions.

15

On completion of the commissioning phase, complete the information sheet at the front of this manual. 

Hand over the installation to the owner and demonstrate how the system works plus basic fault resolution and safety 

procedures. Make sure that this important document is kept in a safe accessible place.

IF IN DOUBT ASK

Handover Instructions

No.

Description

when done

1

Fill in all the details on this Boiler manual.

2

Instruct the owner/users on the correct operation of this heating system, this includes how to turn the system on and off, 

adjust the time and temperature settings.

3

How to turn the heating system off in summer and on for winter.

4

Where all the major items are, their functions and how to check and turn them on or off. Simple fault resolution i.e. power on.

5

How to check and remove air in the radiators. Give them a bleed key.

6

The importance of this SERVICE RECORDS, keeping safe & accessible when required.

7

Recommend that the boiler should be serviced anually and that the service is recorded withing the allocated area of the 

boiler installation manual.

Summary of Contents for VICTRIX PRO 55 1 A

Page 1: ...VICTRIX PRO 55 1 A Wall mounted heating only boiler User Installation Instruction Manual AU...

Page 2: ......

Page 3: ...rder to install the product correctly Maintenance must be carried out by Authorised Service Personal The appliance must only be destined for the use for which it has been expressly declared Any other...

Page 4: ...ting 24 2 7 Info menu 26 2 8 Boiler shutdown 26 2 9 Restoring central heating system pressure 26 2 10 System drainage 26 2 11Anti freeze protection 26 2 12Case cleaning 26 2 13Decommissioning 26 3 Boi...

Page 5: ...ell as their eventual replacement withappliancesand or equivalent components Installation must be carried out according to regulation standards AS NZS 5601 or Local Authority laws Attention these boil...

Page 6: ...ove ground at least 2 3 of the aeration surface must be flush with the floor with a minimum height of 0 2 m The aeration openings must be at least 2 m for heating capacities not exceeding 116 kW and 4...

Page 7: ...in case of supply from LPG depot New LPG storage tanks may contain residual inert gases nitrogen that degrade the mixture delivered to the appliance causing problems with boiler operation Due to the...

Page 8: ...t Heating decline any responsibility for damage or physical injury caused by failure to connect the boiler to an efficient earth system or failure to comply with the reference standards Also ensure th...

Page 9: ...heat adjuster via 2 wires Thermostat electrical connection Fig 1 5 Thermoregulation electrical connections must be carried out on the boiler terminal board eliminating jumper X40 Thermostat or On Off...

Page 10: ...on Type C configuration sealed chamber and fan assisted The boiler leaves the factory with B23 configuration to change the configuration of the boiler to type C sealed chamber and fan assisted disasse...

Page 11: ...t 1 3 m Terminal complete with vertical exhaust 80 Exhaust m 3 DUCT TYPE Equivalent length in m of concentric pipe 80 125 Concentric pipe 80 125 m 1 1 0 m Concentric bend 90 80 125 1 9 m Concentric be...

Page 12: ...ent space to carry out the tests required by law upon commissioning The intake exhaust terminal if properly in stalled is pleasant to look at on the outside of the building Make sure that the external...

Page 13: ...er 1 up to the relevant groove Fix it to the lid using the previously disassembled sheet steel plate 3 Installation of the fake aluminium tile replace the tiles with the aluminium sheet 5 shaping it t...

Page 14: ...m length MAX L Fig 1 16 The kit with this configuration can be extended up to a max measurement of 30 0 m with Victrix Pro 55 1A including the terminal Using the 80 vertical terminal for direct dis ch...

Page 15: ...and external 4 wall sealing plate has been fitted This will ensure sealing and joining of the elements making up the kit Horizontal kit 80 with exhaust in flue Kit assembly Fig 1 22 install the 80 be...

Page 16: ...em refer to the technical standard in force This divides the systems and therefore the start up operations into three categories new systems modified systems re activated systems In particular for new...

Page 17: ...of 18 C between flow and return During DHW mode the pump always runs at the maximum speed Pump release If after a prolonged period of inactivity the circulation pump is blocked unscrew the front cap...

Page 18: ...densation module cover 12 Igniter 13 Ignition electrode 14 Flue probe 15 Condensing module air vent valve 16 Fumes hood 17 Sample points air A flue gas F 18 Heat exchanger safety thermal fuse 19 Manua...

Page 19: ...circuit breaker switches andofthethermometer notsuppliedasstandard with the boiler must be set up as described in the installation instructions in compliance with theprovisionsofthe R collection Whene...

Page 20: ...ng circuit pump CMI 1 13 Zone 2 central heating circuit pump CMI 2 14 Zone 3 direct circuit pump CD 15 Storage tank unit feeding pump 16 Zone 1 safety thermostat CMI 1 17 Zone 2 safety thermostat CMI...

Page 21: ...the heating system if anti freeze is not used b shut off all electrical water and gas supplies N B in the case of maintenance interventions on the boiler that lead to the closure of one or both system...

Page 22: ...24 Pump running 25 Summer mode 2 5 USING THE BOILER Before ignition make sure that the system is full of water checking that the manometer 5 indicates a base value at which the system has been design...

Page 23: ...maintain the previous setting 2 4 2 5 Stand by mode by pressing buttons A and C at the same time it is possible to place the boiler in stand by In this mode the boiler is considered powered on but no...

Page 24: ...re The error may be caused by a poor thermal probe contact or a system with excessive thermal inertia Press the Reset button 1 0A17 Poor thermal return NTC probe contact During boiler operation the bo...

Page 25: ...on incorrect in stand by With the boiler in stand by the board detects an anomalous difference between the NTC probe flow and return temperatures The error may be caused by a failure in one of the two...

Page 26: ...ned frequently filling must be carried out with suitably treated water to eliminate hardness that can cause lime scale 2 12 CASE CLEANING Use damp cloths and neutral detergent to clean the boiler casi...

Page 27: ...ified check sealing efficiency of water circuits check ventilation and or aeration of the instal lation room where provided ensure the gas inlet working pressure is correct 1 1 Kpa Natural Gas 2 75 Kp...

Page 28: ...Fan M30 Three way valve optional Configure the corresponding parameters when connecting in simple cascade or when con necting in system side flow probe or D H W pump S1 Main switch Y1 Gas valve 1 Exte...

Page 29: ...10 Flue probe B25 System flow meter E4 Safety thermostat E5 Heat exchanger safety thermostat manual reset E13 Flue safety thermofuse M1 Boiler circulator pump M20 Fan S5 Absolute pressure switch S20 O...

Page 30: ...inlet Clean contact Max 230 Vac 1 A Key B1 System flow probe NTC B2 Domestic hot water probe NTC B4 External probe M2 Plant CH pump M30 3 way valve Note probe B1 B2 B4 Connection cable diameter 3 7 m...

Page 31: ...ve is open Incorrect adjustment of the gas valve check the correct calibration of the gas valve Irregular combustion or noisiness It may be caused by a dirty burner incorrect combustion parameters int...

Page 32: ...d by multiplying the value displayed by 50 P26 120 0 P12 Boiler s modulation ratio It defines the boiler s modulation ratio Do not modify 0 100 10 P13 Boiler power Used to calculate the boiler power i...

Page 33: ...46 P31 Unit of measurement This defines the unit of measure on the display whether metric or Imperial 0 127 C kW 128 256 F kBTu h 0 P32 Min Heating Set Temp Limits the minimum value of the heating se...

Page 34: ...e turn the adjustment screw 3 in a clockwise direction and vice versa to decrease it Calibration of maximum CO2 When you finish the minimum CO2 adjustment turn the boiler on and start the chimney swee...

Page 35: ...obe must be connected to terminals S1 and S2 and parameter P38 must be set up whereas the pump must be connected to termi nals C and D If there is a DHW circuit it can be connected via an external 3 w...

Page 36: ...e replaced at least every two years regardless of their state of wear Check that the burner is intact that it has no deformations or cuts and that it is properly fixed to the combustion chamber lid ot...

Page 37: ...to de tach it from the central hooks and then slide it downwards take the two clamping screws out 4 from the control panel with their rings 5 press the two side hooks 7 and tilt the control panel 6 re...

Page 38: ...38 3 15 1 6 8 9 9 12 12 10 11 13 13 13 13 A A Rif A 7 7 INSTALLER USER MAINTENANCE TECHNICIAN Ref A...

Page 39: ...43 6550 3 98 6450 49 0 223 1 5 32 6430 3 91 6330 47 0 213 4 5 09 6170 3 74 6060 45 0 204 0 4 87 5910 3 57 5810 43 0 194 6 4 64 5660 3 41 5550 41 0 185 4 4 42 5410 3 25 5300 39 0 176 3 4 21 5160 3 09 5...

Page 40: ...06 8 99 7 Efficiency 40 30 Nom Min 107 4 103 5 Heat loss at casing with burner Off On 80 60 C 0 30 0 90 Heat loss at flue with burner Off On 80 60 C 0 03 1 80 Central heating circuit max operating pre...

Page 41: ...41 INSTALLER USER MAINTENANCE TECHNICIAN 3 27 EXPLODED BOILER DIAGRAM 17 05 17 3 024493 5647076 SERIAL NUMBER START OF SERIES VICTRIX PRO 55 1 A 82D...

Page 42: ...r 10x5 2x1 90 1 8599 Washer 4 3x12 91 3 023387 Flue hood group 92 1 025278 Plug for flange with sample points 93 1 036108 Flue exhaust pipe d 80 94 1 020368 Lip gasket d 80 95 1 034463 Frame 96 1 0352...

Page 43: ...inhibitor was used Quantity Litres Has a system filter been installed Yes No HEATING MODE measure and record Burner inlet gas working pressure at maximum rate Kpa OR gas inlet pressure Kpa Central he...

Page 44: ...lights and heats the water Check gas flame is the correct colour and for gas and water leaks as the system heats up 11 Check that heat is circulating to all radiators through the manual or thermostat...

Page 45: ...ame Telephone No Plumbing Licence No Record At max rate CO ppm CO CO CO Ratio At mim rate CO ppm CO CO CO Ratio Comments Signature SERVICE 02 Date Engineer name Company name Telephone No Plumbing Lice...

Page 46: ...one No Plumbing Licence No Record At max rate CO ppm CO CO CO Ratio At mim rate CO ppm CO CO CO Ratio Comments Signature SERVICE 10 Date Engineer name Company name Telephone No Plumbing Licence No Rec...