Rack Installation Instructions

For the 11000 VA 5U uninterruptible power supply and 11000
VA 3U extended battery module

Use the instructions in this document to install the IBM

®

11000 VA LCD 5U Rack UPS and IBM 11000 VA

UPS 3U Extended Battery Module in a rack cabinet.

Review the documentation that comes with your rack cabinet for safety and cabling information.

When you install the uninterruptible power supply (UPS) or extended battery module in a rack cabinet,
observe the following precautions:

v

The extended battery module and UPS internal battery and chassis are heavy. Make sure that you have
the minimum number of persons and equipment that are required to safely lift the components. See
step 7c on page 5 and Table 1 on page 6.

v

Make sure that the room air temperature is below 35°C (95°F).

v

Do not block any air vents; usually 15 cm (6 in.) of air space provides proper airflow.

v

Plan the device installation starting from the bottom of the rack cabinet.

v

Install the heaviest device in the bottom of the rack cabinet.

v

Do not extend more than one device out of the rack cabinet at the same time.

v

Connect all power cords to properly wired and grounded electrical outlets.

v

Do not overload the power outlet when you install multiple devices in the rack cabinet.

You will need a Phillips screwdriver to install the UPS or extended battery module in a rack cabinet.

Note:

The illustrations in this document might differ slightly from your hardware.

The following parts come with the rack mounting kit:

v

One right adjustable rail

v

One left adjustable rail

v

Four adapter plates with adhesive (for round hole racks)

v

Sixteen M5 x 16 mm Phillips screws

Note:

Removing the rack doors and side panels might make installation easier. See the rack cabinet
documentation for more information.

Summary of Contents for 11000 VA LCD 5U

Page 1: ...95 F v Do not block any air vents usually 15 cm 6 in of air space provides proper airflow v Plan the device installation starting from the bottom of the rack cabinet v Install the heaviest device in...

Page 2: ...ge v Disconnect the attached power cords telecommunications systems networks and modems before you open the device covers unless instructed otherwise in the installation and configuration procedures v...

Page 3: ...rack cabinet complete the following steps 1 For racks with round holes only Install one adapter plate on each of the ends of the right and left rails a Locate the four adapter plates that come in the...

Page 4: ...S or extended battery module 4 Secure each rail to the front of the rack with two M5 x 16 mm screws Make sure that the rails are on the inside of the rack cabinet mounting flanges and the letter on ea...

Page 5: ...humbscrew on the right battery retention bracket 1 slide the bracket to the left 2 rotate the bracket out 3 and then remove it R c Remove the left internal battery module Important Each internal batte...

Page 6: ...nded battery module handling requirements Machine type model or part number Product description Weight Handling requirement 5395 9KX 11000 VA 5U rack UPS 35 kg 77 lb without internal battery modules T...

Page 7: ...of arcing might occur when you connect the batteries This is normal and does not damage the unit or present any safety concern c Reinstall the right battery retention bracket 1 Slide the right battery...

Page 8: ...left battery retention bracket 4 12 Install the bezel v For a UPS a Locate the upper and lower bezels that come with the UPS The upper bezel has an opening for the liquid crystal display LCD b To inst...

Page 9: ...e LCD on the front of the UPS For more information about installing and operating the UPS and extended battery module see the Installation and Maintenance Guide that comes with the UPS Important Befor...

Page 10: ...6 min 2 Make sure that the UPS internal batteries are disconnected For more information see the Installation and Maintenance Guide on the IBM Documentation CD that comes with the UPS 3 Remove the fou...

Page 11: ...ezel OK OK 100 6 min 2 Remove the four screws that secure the shipping bracket and the UPS to the rack cabinet Keep the four screws OK OK 100 6 min Shipping bracket 3 Remove the shipping bracket and s...

Page 12: ...ited States other countries or both Other company product or service names may be trademarks or service marks of others Printed in USA Copyright IBM Corporation 2011 US Government Users Restricted Rig...

Reviews: