Procedure
Step 1
Check that the cables are correctly connected.
Step 2
Check that the input voltage of the RRU3931E is 110 V AC to 240 V AC, and the frequency
ranges from 50 Hz to 60 Hz.
Step 3
Power on the RRU3931E. Wait 3 to 5 minutes and then observe the indicator status of the
RRU3931E. If the RUN indicator blinks (on for 1s and off for 1s) and the ALM indicator is
off, the RRU3931E is working properly.
NOTE
l
A RRU3931E takes about 3 minutes to complete the startup procedure, during which the indicator
status is negligible.
l
During a startup, a RRU3931E reads and writes the flash memory and therefore the indicators
blinking quickly may blink irregularly for 1s to 2s, which does not affect services.
----End
1.11 References
This section describes reference information and common operations involved during
installation.
1.11.1 Assembling a Shielded RJ45 Connector and an Ethernet
Cable
This section describes how to assemble a shielded RJ45 connector and an Ethernet cable. A
straight-through cable is used as an example.
Context
Figure 1-40
shows the components of an RJ45 connector and an Ethernet cable.
RRU3931E
Installation Guide
1 RRU3931E Installation Guide
Issue Draft A (2016-03-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
43