7
Installing the RTN 310 at a 1+1 LAG Mode Site
26/27 >>
EG4Pboard
1
2
3
4
RTN 900
RTN 310
6
7
6
8
8
5
6
9
10
8
7
7
P&E
COMBO
P&E
COMBO
Connected to
the NMS
1 to 5
1.
Cover unused ports with caps. Reserve the removed caps. Before installing the RTN 310, remove the protective cover and film on the antenna port. Otherwise, the signal transmission will be affected.
2.
Different methods can be used to change the polarization direction of antennas. If the method provided in this document is not suitable for the type of antenna you have, use the method provided in the installation manual delivered with your antennas.
3.
The polarization direction of antennas is vertical by default. If the planned polarization direction is horizontal, change the polarization direction to horizontal.
4.
If an antenna with a diameter of 0.6 m or less is used in a direct mount scenario, you may install the RTN 310 and a hybrid coupler on the antenna and then hoist them both into position on the tower.
5.
Before installing a cable, bind the cable section that links the cable connector to the pole. This will protect the cable connector from damage. Be sure that the length of cable running from the binding point to the RTN 310 is sufficient to attach the cable connector to the
Ethernet service port on the RTN 310.
Installing the RTN 310
Install the PGND cable of the RTN 310.
Waterproof the ground clip.
Install a GE cable.
Follow the antenna installation guide to
install the antenna.
• Install a ground clip.
• Select a ground point for the GE cable.
• Lay out the GE cable.
• Install a GE cable.
• Attach a yellow label to the cable
according to the plan.
Optional:
Change the polarization direction
of the antenna to horizontal.
Mount the RTN 310 on the hybrid coupler.
Install the hybrid coupler on the antenna.
Apply petroleum jelly around the exterior side
of the hybrid coupler feeds and the RTN 310.
Install a 1+1 cascade fiber.
Check the installation.
Installation procedure
Power on the RTN 310.
1
Use a USB flash drive to load
NE data.
2
Use the Web LCT to configure
NE data.
3
Align antennas.
4
Site commissioning procedure
Grounded
through the
ground clip