3.3.2 Hoisting Scenario
Procedure
Step 1 Determine the installation position.
NO TICE
The following describes only the requirements for the spacing between cabinets
for the components to be hoisted. The components to be hoisted must be
prepared based on the actual situation.
● The distance between hanging rods and the cabinet top must be at least 300
mm. The straight line section must be at least 443 mm away from the cabinet
top. Otherwise, the hanging rods or the NMW may interfere with the cable
trough or door.
● Install a group of hanging rods every 600 mm.
● Hanging rods cannot be installed around a column. You need to adjust their
locations.
● The cables from the power distribution unit to the cabinet rPDU are not
prefabricated and need to be prepared onsite. For details, see the appendix
"Preparing Load Cables."
Step 2 For details about how to install the NMW and cables, see the instructions in the
support-mounting scenario.
----End
3.4 Installing Cables
3.4.1 Cable Routes
NO TICE
The figures use the scenario of maintenance on both sides as an example.
New Main Way 2.0
User Manual