About electrostatic discharge
17
Chapter 2: Install the server hardware
This section contains the following topics:
•
About electrostatic discharge
•
Unpack the shipping carton
•
Install the server enclosure in a rack
•
Mount the enclosure in the rails
•
Connect the network cables
•
Connect the power cables
•
Organize the cables
•
Power on the system
•
Attach the OmniCube bezel
To install the server hardware, you must unpack all hardware components, install the enclosure in a rack, connect
the power and network cables, and power on the server.
About electrostatic discharge
You must protect sensitive hardware from electrostatic discharge (ESD), which can damage electronic
components.
To protect hardware from ESD:
• Ensure the server hardware is fully grounded at all times to prevent damage from electrostatic
discharge.
• When not installed in a rack, store server hardware in its original packaging or place on a sturdy
surface that is protected from electrostatic discharge.
• When handling server hardware components, always use the electrostatic wrist strap provided or a
similar form of ESD protection.
Unpack the shipping carton
You unpack the shipping carton to prepare the system hardware components for installation.
Before you begin
• The OmniCube servers are heavy. You must have at least one other person to help you lift and unpack
the carton, and SimpliVity recommends the use of a datacenter equipment lift.
• You have cut the pallet shipping straps, which might have considerable tension, using an appropriate
tool and safety wear.
Procedure
1.
Remove the shrink wrap from the palleted cartons and carefully cut any straps that hold the cartons to
the pallet.
2.
To orient the carton for ease of unpacking and racking, locate the black circle printed on the side of the
carton. This is the front of the system enclosure.