6.7 Filling Unit with water
Unclip the Chiller lid and fill the tank with water until water flows out the overflow tube into the drip tray.
6.8 Commissioning
Before running unit, sanitise product lines using a beer line cleaner.
Connect the chiller with a suitable extension lead to an appropriate socket outlet and switch unit on.
The compressor, condenser fan and agitator motor should all operate.
When the ice bank is fully formed (approx. 3 hrs.) the compressor and condenser fan will cycle off,
but the agitator will run continuously.
Operate dispensing taps and check temperature and flow of the product.
If the product is heady (excessive foam) the CO
2
gas pressure on the keg may need to be adjusted
or the beer flow control inside the chiller water tank may need adjusting.
Check all connections for leaks.
7. Scheduled
Maintenance
Warning
The Chillers must not be cleaned by a water jet.
Access to the service area restricted to persons having knowledge and
practical experience of the appliance, in particular as far as safety and
hygiene are concerned.
The following Chiller routine maintenance should be performed at the intervals listed.
7.1. Scheduled Maintenance
7.1.1.
Weekly
As per brewery instructions, ensure weekly sanitisation of the whole beer system is
carried out, including keg couplers, beer lines, chiller coils and taps.
7.1.2.
Monthly
Disconnect the machine from the power supply.
Clean condenser with a brush or blow down with compressed air..
Check the tank level. Fill if necessary.
Check operation of the agitator.
Check for beer leaks.
Reconnect the machine to the power supply.
7.1.3.
Yearly
Disconnect the machine from the power supply.
Remove drain plug to drain the water bath, check interior of the tank, clean product coils
and evaporator if necessary to remove any accumulated deposits.
Check agitator operation
Inspect agitator blade for deposits and wear.
Reinsert drain plug and re-fill tank with water.
Reconnect power supply and start machine.