Horne Engineering Ltd
Issue 7, November 2018
2
Every HORNE TSV1-3 is supplied with an integral WRAS approved single check valve and integral large
surface area strainer. The Shower Panel terminates in 15mm copper pipes for hot and cold supplies. The
hot pipe is on the left, and cold on the right,
when viewed from the user’s perspective.
INSTALLATION
The surface mounting enclosure is supplied with fixings to attach it to a wall. However consideration
should be given to the type of wall fittings required, as different substrates will require different fittings.
Recommended Mounting Heights
T105, T107, T108 Panels
Bottom of panel should be 1.0 metre from finished floor level.
T016 Panel (swivel-head, shown p13)
Bottom of panel should be 1.1 metres from finished floor level.
1) Position the Pre-Plumbed Enclosure
Identify a suitable position for the Enclosure and mark a line on the wall level with the top of the
casing. Mark a point on the wall which is on the required centreline for the Casing 15mm below
the line of the top of the casing for the support screw (See Fig 1).
2) Install the Support Screw
Drill a 7.0mm dia. hole in the wall and insert a wallplug and screw, leaving the head of the screw
11-13mm from the wall surface. Note that a stainless steel screw is supplied for this (corrosion
resistant).
3) Hang the Enclosure on the Support Screw
Release the top cover of the pre-plumbed enclosure by removing the four screws. Hang the pre-
plumbed enclosure on the support screw by the larger hole in the middle of the back strap and let
this take the weight of the enclosure. See Fig 2.