Acoustic alarm switch   

Position „On“ 

The built-in acoustic alarm is activated. Together with the 
red LEDs “Alarm“and “Failure“ the built-in acoustic alarm 
will start if the level of the medium is above the alarm level. 
The alarm is automatically reset when the liquid level has 
been lowered below the alarm level. 
 

Position „Off“ 

The built-in acoustic alarm is not activated.  
 
The controller front cover features 

Light-Emitting Diodes 

(LEDs)

 for indication of operating conditions : 

 
Yellow LED „Incorrect phase sequence“ (only 3-ph 
models) 

The yellow LED in the front cover of three-phase controllers 
indicates wether the phase sequence of the mains connec-
tion is correct. If the LED is illuminated, the phase se-
quence is wrong. 

Note :

 This function does not prevent the motor from start-

ing and rotating in the wrong direction because it does not 
measure the phase sequence to the motor. 
Therefore, the direction of rotation of three-phase pumps 
must always be checked if the cable between pump and 
controller has been removed. 
 

Green LED „Operation“ 

The green LED illuminates when the pump is operating. 

 

Red LED „Alarm“ and „Failure“

 

- Permanent Signal 

The red Alarm-LED illuminates in case of to high liquid level 
in tank. Together with the red LED, the built-in acoustic 
alarm is activated if the switch in the front cover is in posi-
tion „On“. Furthermore, the external fault signal device, if 
fitted, is activated. 
If the red Alarm-LED illuminates together with the green 
LED, the pump operates, but the liquid level in the tank is 
above the alarm level. The alarm is automatically reset 
when the liquid level has been lowered below the alarm 
level. 
If the red LED illuminates together with the LED „Failure“, 
the pump was stopped by thermal cutout. In this case, push 
the „Reset“ switch. If the pump still does not work, please 
contact your HOMA service. 

 
Red LED „Failure“ 
- Flash Signal 

The Failure-LED flashes when the annual maintenance is 
recommended after 2 months. 
 

Deactivating of „Maintenance flash“:  

Set the operation switch in position „Aus/Off“, then press 
the „Reset“-button. After releasing „Reset“ the LED „Alarm“ 
lights up for approx. 1 second. Within this time set the op-
eration switch in position „Auto“. The flash light extinguish. 
 

Reactivating of „Maintenance flash“ (only possible by 
using ServCom Service-Controller):  

Reset the maintenance counter in the ServCom menu. 
Subsequently set the operation switch in position „Aus/Off“, 
then press the „Reset“-button. 

 

Note:  

Deactivating „Maintenance flash“ is possible starting from 
version 1.0d of the pump control (see menu in ServCom). 
„Maintenance flash“ is deactivated, if „!“ appears behind in 
ServCom the version No;  
„Maintenance flash“ is activated, if „!“ behind the version 
No. is missing. 
 

Red LED „Alarm“ 
- Flash Signal 

The Alarm-LED flashes when the control unit has monitored 
several pump operation circuits longer than 2 minutes 
each. Please contact your HOMA service. 

 

 

6.3. Check of Direction of Rotation 

1 Ph-pumps do not require any check, as  
they always  run with the correct direction of 
rotation. 
 
Put the pump vertical on the ground and lift 
one edge. Start the motor. Viewed from 
above, the unit must jerk anti-clockwise, as 
the correct direction of rotation is clockwise. 

 

If the direction of rotation is wrong, inter-
change two of the phases of the electric 
power supply. Using an original HOMA con-
trol box with CEE-plug, this may be done by a 180° turning 
of the small round pole-socket at the plug-end with a 
screwdriver. 

 
7. Installation 

If the pump is installed in a sump, the sump opening 

must be covered with a tread-safe cover after installation. 

The operator has to prevent damage through the flood-

ing of rooms caused by defects of the pump through the 
use of appropriate measures (e.g. installation of alarm 
units, backup pump or like that). 
Fasten the tank to an even floor with expansion bolts. 
Before installing the disposal units make sure that the all 
national instrucions and the general measures for health 
protection and industrial protection for the installation of 
disposal units (DIN 1986) are observed.  
 
Furthermore please pay attention to the hints below: 
 

 

Install the unit in that way, that the operation and ser-
vice elements are easily accessable. Make sure that 
there is enough space (approx. 50 cm) between the 
horizontal inlet and any wall. 

 

Mount a gate valve into the inlet pipe and the dis-
charge pipe to guarantee an easy service or demount-
ing of the unit . 

 

To avoid sediment build-up in the discharge pipe, the 
pipe, and the liftimg station, should be dimensioned for 
a water velocity of minimum 0,7 m/s, for vertical pipes, 
however, not lower than 1,0 m/s. 

 

The incoming sewer could be ensues at the horizontal 
inlet through a WC-direct connection with 180 mm, 210 
mm, or 250 mm, or a DN 100 or DN 50 effluent pipe. 
Vertical inlets (DN 100 / DN 40 and DN 150 / DN 40) 
for service pipe lines are existing. Cut off the blanked 
off the vertical or horizontal inlet and connect a incom-
ing sewer inlet which correspond to the diameter of the 
inlet. 

 

Summary of Contents for Sanistar C Series

Page 1: ...nal Betriebsanleitung Original Instruction Manual HOMA Pumpenfabrik GmbH 06 2012 Industriestr 1 D 53819 Neunkirchen Seelscheid Abwasser Hebeanlagen Compact sewage disposal units Baureihe Series Sanist...

Page 2: ...ite 3 Page 10 Seite 16 Page 16 Seite 16 Page 16 Seite 18 Page 18 DEUTSCH ENGLISH Installationsbeispiele Installations Bauma e Dimensions Ersatzteilliste und Ersatzteilzeichnungen Spare part list and s...

Page 3: ...einschl gigen grundlegenden Sicherheits und Gesundheitsanforderun gen der EG Maschinenrichtlinien entsprechen Bei einer nicht mit uns abgestimmten nderung der Pumpen verliert diese Erkl rung Ihre G lt...

Page 4: ...allverh tungsvorschriften sowie die allgemein anerkannten Regeln der Technik sind einzuhalten Wir wei sen darauf hin dass wir nach dem Produkthaftungsgesetz f r Sch den die durch unser Ger t verursach...

Page 5: ...ngerer Lagerung ist die Anlage gegen Feuchtigkeit W rme oder Frost zu sch tzen 6 Elektroanschluss 6 1 Allgemeines Eine fachm nnische Pr fung vor Inbetriebnahme muss sicherstellen dass die geforderten...

Page 6: ...danach nicht einwandfrei arbeitet infor mieren Sie bitte unseren Kundendienst Rote LED St rung Blinksignal Blinkt zur Information 2 Monate bevor der emfohlene j hrli che Wartungstermin erreicht ist D...

Page 7: ...Hilfe des mitgelieferten elasti schem bergangsst cks auf den Sammelbeh lter montieren Die Entl ftungsleitung ist verstopfungsfrei gegen Abknicken gesichert zu installieren Die Leitung muss in bereinst...

Page 8: ...viceanforde rung detaillierte Informationen ber das F rdermedium vorliegen Bei eventueller Serviceanforderung muss unbedingt vor dem Versand der Pumpe mit HOMA Kontakt aufgenommen werden Informationen...

Page 9: ...Schumacher Meiendorfer Stra e 71 Auf Steingen 20 22145 Hamburg 72459 Albstadt Lautlingen 0 40 6 91 90 90 0 74 31 95 83 24 Karl Heinz Birr Pumpenservice G Meier GmbH Glash ttenweg 60 Gustav Schwab Str...

Page 10: ...ump types in the form in which they are marketed by us con form to the relevant fundamental safety and health re quirements of the EC Machine Directives Sanistar C EC Directives to which the pumps con...

Page 11: ...and guidelines set forth in the operating instructions The same product liability are valid for acces sories 3 Applications and Technical Description 3 1 Applications HOMA disposal units Sanistar are...

Page 12: ...oltage Make sure that the electrical pin and socket connec tions are installed flood and moisture safe Before starting operation check the cable and the plug against damages The end of the pump power...

Page 13: ...in position Aus Off then press the Reset button Note Deactivating Maintenance flash is possible starting from version 1 0d of the pump control see menu in ServCom Maintenance flash is deactivated if...

Page 14: ...cessories Before maintenance or repair disconnect the pump from the power supply to avoid accidental starting of the pump Before maintenance or repair make sure that all rotat ing parts stand still Be...

Page 15: ...eaky or clogging Check the hose and clean or re place Fuses blow due to use of wrong type of fuse Install fuses of the correct type Pump does not stop Pressure hose is leaky or clogging Check the hose...

Page 16: ...Hauptzulauf vertikal Main inlet vertical Direktanschluss Euro WC Zulaufh he 180 mm Direct connection Euro WC inlet height 180 mm Direktanschluss H nge WC Zulaufh he 250 mm Direct connection hanging WC...

Page 17: ...150 DN 40 6 Entl ftungsstutzen DN 70 Air vent DN 70 7 Reinigungs ffnung Clening cover 8 Kugelr ckschlagklappe DN 80 Soft ball check valve DN 80 9 Elastisches bergangsst ck Elastic union piece 10 Flan...

Page 18: ...9 03 Zylinderschraube DIN 912 A2 9 04 U Scheibe 9 05 Winkel Einschraubstutzen 9 06 Schlauchschelle 9 07 PVC Gewebeschlauch 9 08 Typenschild neutral 10 01 Elektronik Einzelsteuerung 14 Spare Part List...

Page 19: ...19 14 2 Ersatzteilzeichnung Spare part drawing...

Page 20: ...Nr Bezeichnung Menge Lieferanschrift Unterschrift Firmenstempel 15 Order Sheet for Spare Parts To HOMA Pumpenfabrik GmbH D 53819 Neunkirchen Seelscheid Fax 49 22 47 7 02 44 Pump type see pump label Y...

Page 21: ...xisch nein ja welche Stoffe _____________________ tzend nein ja welche Stoffe _____________________ mikrobiologisch nein ja welche Stoffe _____________________ explosiv nein ja welche Stoffe _________...

Page 22: ...______________ corrosive no yes which substance __________________ microbiological no yes which substance __________________ explosive no yes which substance __________________ radioactive no yes whic...

Page 23: ...21...

Page 24: ...22...

Reviews: