7 of 22
JAN 2022 REV. C
EAZ0080V72A
4.0
Positioning of Jacking Beam on Lift
Note:
The Jack Beam must be positioned on the lift correctly prior to usage.
1. Place Jack Beams on runway tracks at front and rear of lift with the pump of each
facing to the front and rear.
a. Adjust the roller adapter to center the jack body between jack rails.
b. Ensure wheels are on the tracks and roll freely.
c. Tighten roller adapter jam nuts
2. Attach recoil hose to the bulkhead fitting at the rear of each Jack Beam, and then
other ends to the ‘T’ fitting on lift.
a. The Jack Beam is shipped pre-assembled to install at the front of the lift.
The air connection bracket is on the rear left side of the Jack Beam.
b. To install the Jack Beam at the rear of the lift, the air connection bracket
must be removed and reinstalled on the rear right side. Disconnect the
1/4” polytube, reroute, cut to length and reinstall.
c. Check reservoir for hydraulic oil and fill as needed.