2
PREPARATION
Model
Dimensions
A
B
deg.
mm
deg.
mm
RUA-13AT3S
0.4
15
0.6
15
RUA-15AT3S
0.4
15
0.6
15
RUA-20AT3S
0.4
14
0.6
20
RUA-30AT3S
0.4
17
0.6
20
Fig. 2. Foundation Gradient
Model
Dimension A
mm
RUA-20AT3S
1,836
RUA-30AT3S
2,316
For Models RUA-13AT3S and RUA-15AT3S For Models RUA-20AT3S through RUA-30AT3S
Fig. 3. Recommended Concrete Curbs
1.3 Placing the Unit
Tools and Instruments
–
Pincers, Wrenches,
Facilities to Transport and Place the Unit.
Transportation
–
Transport the unit as close to
the final installation location as practical before
unpacking is performed. Keep the unit upright.
When transporting the unit after unpacking has
been performed, take note of the following.
Rolling
–
Place three equal - sized rollers under
the base frames. Each roller must carry both of
the outer frames, and must be situated to balance
the unit (refer to the center of gravity in Fig. 4).
Lifting by Forklift
–
Insert the forks under the base
frames from the indicated direction in Fig.4. Lift the
unit, exercising care to catch both of the outer frames.
Rigging
–
Apply spreader bars to the top of the unit,
in order to prevent damage to the unit due to cable
scratches.
Unpacking
–
Follow the instructions marked on the
packing.
NOTES:
1. Keep the unit covered with a vinyl cover during installation work for peripheral equipment.
2. Do not expose the unit under the direct sunshine.