Installation instructions Art. No. 36185-36190
Page 2 of 2
Status 03.2012
This product may only be installed by a qualified specialist electrician.
Before the installation is done, the connection lines to the building must be switched free from voltage
and protected against being switch on again. Take the appropriate automatic circuit breakers out of the
junction box in the building.
Decide upon the place of installation. Keep a minimum clearance from 0,5 m to the lit surfaces.
Make sure that the base is suitable to support the weight of the light permanently and reliably. Mark the
position of the screw holes.
Continue by drilling the screw holes with a suitable drill. Make sure that no lines are damaged during
installation.
Continue by feeding the power supply cable through the cable input gasket.
Now connect the connection lines at building installation to the screw terminals of the light . Connect up
the yellow-green ground wire first of all and then the other two lines. The brown (or black) cable is
usually the phase conductor, connect this to the terminal marked with an "L". The blue conductor must
be connected to the terminal marked with an "N".
Protect all the cables and insulations from possible damage.
Check again to make sure you have made a proper connection and recluse the installation housing.
Switch on the circuit breakers of the junction box in the building again.
Replace each broken screw
The rating plate must not be removed.
Heitronic
®
H. Vollmer GmbH
Allmendring 29
D-75203 Königsbach-Stein