25
Heat & Glo • Cerona-36, Cerona-42 • 2106-900 Rev. Q • 8/14
E. Adding Vent Components
To Install the Heat Shield:
1. determine if the heat shield is required. do so by measuring
the vertical distance between the top horizontal surface of
the elbow to any combustible surface above. If the distance
is more than 4 inches, the heat shield is
NOT
required. If it
is 4 inches or less, the heat shield
IS REQUIRED
. Install
per the following steps. See Figure 7.4.
CORRECT
INCORRECT
2. Fasten the shield in place using the four pilot holes
provided in the part. The shield should be oriented such
that the 13 1/8 inch dimension (longest dimension) is
running in the same direction the elbow is pointing. The
shield should be centered directly above the elbow, and
positioned so that it creates a 1/2 inch airspace between
the shield and the combustible surface. See Figure 7.5.
• If the combustible materials are not in place at the time
of install the elbow heat shield may be screwed to the
exhaust pipe (see Figure 7.6). Cut the tabs as shown
and bend down. Secure the heat shield to the pipe
maintaining 3 inch to 4 inch between the pipe and shield.
Refer to Cinch Pipe and Termination Cap installation in
-
structions.
• Continue adding vent components, locking each
succeeding component into place.
• Ensure that each succeeding vent component is securely
fitted and locked into the preceding component in the
vent system.
• 90º elbows may be installed and rotated to any point
around the preceding component’s vertical axis. If an
elbow does not end up in a locked position with the
preceding component, attach with a minimum of two (2)
sheet metal screws.
F. Install Support Brackets
Refer to Cinch Pipe and Termination Cap installation in
-
structions.
Figure 7.4
Figure 7.6
Figure 7.5
Fire Risk.
Installation of this appliance may require the use
of heat shield 385-290 above the first 90
0
elbow
in the venting system.
WARNING
HEAT
SHIELD
3” MIN.
(76mm)
COMBUSTIBLE
SURFACE
COMBUSTIBLE SURFACE
DIRECTION
UP
HEAT SHIELD
90º ELBOW
SCREW
3 in.
(76 mm)
Make sure that the fiberglass rope ring supplied in the
manual bag seals between the first vent component and
the outer appliance wrap. See Figure 7.3.
Figure 7.3 Fiberglass Rope Ring
FIRST VENT
COMPONENT
FIBERGLASS
ROPE RING
OUTER
WRAP