Gas Fired Boiler
11
Harsco Industrial, Patterson-Kelley Technical Service 1.877.728.5351
3
I
NSTALLATION
3.1 Receiving and Storage
3.1.1 Initial Inspection
Upon receiving the boiler, inspect it for signs of shipping damage.
Some damage may be hidden. Unpack the boiler, open the front
and side doors and inspect the boiler. Verify that the total number
of pieces shown on the packing slip agrees with those actually
received.
3.1.2 Storage Prior to Installation
If the boiler is not installed immediately, it must be stored in a
location adequately protected from the weather, preferably indoors.
If this is not possible, then it should remain in the shipping container
and be covered by a tarpaulin or other waterproof covering.
3.2 Compliance with Codes
The boiler with standard components and with many options
complies
with American National Standard/CSA Standard ANSI
Z21.13/CSA 4.9, latest edition, Gas-Fired Low Pressure Steam and
Hot Water Boilers.
The SC-2000 heat exchanger is constructed and stamped in
accordance with ASME Boiler and Pressure Vessel Code, Section
IV (160 psig maximum operating pressure).
The SC-3000 and SC-4000 contain two separate heat exchangers
constructed and stamped in accordance with ASME Boiler and
Pressure Vessel Code, Section IV, and Section VIII – Division 1
(160 psig maximum operation pressure).
Installation of the boiler must conform to all the requirements of all
national, state and local codes established by the authorities having
jurisdiction or, in the absence of such requirements, to the National
Fuel Gas Code, ANSI Z223.1/NFPA 54 latest edition in the U.S. In
Canada, the equipment shall be installed in accordance with the
current Installation Code for Gas Burning Appliances and
Equipment, CAN/CSA-B.149, latest edition, and applicable
Provincial Regulations for the class, which should be carefully
followed in all cases. Authorities having jurisdiction should be
consulted before making any installation.
Where required by local codes, the installation must conform to
American Society of Mechanical Engineers Safety Code for
Controls and Safety Devices for Automatically Fired Boilers (ASME
CSD-1).
In the Commonwealth of Massachusetts (a) this unit must be
installed by a licensed pipe fitter/plumber, (b) field installed gas
cocks must be “T” handle type, (c) piping of condensate shall
conform to the State Plumbing Code, and (d) refer to the
Massachusetts Supplement for further details.
Installation and service must be
performed by a qualified installer,
service agency, or gas supplier.
Failure to install the equipment in
accordance with this manual could
result in an unsafe operating
condition.
N
OTICE
!
Controls and other equipment that
are damaged or fail due to weather
exposure are not covered by
warranty.
The wheels provided with this
boiler are for positioning purposes
only. When positioning this boiler,
maintain positive control of it at all
times. Do not attempt to move the
boiler on surfaces that are not
level. Failure to heed this warning
could result in personal injury or
death.
N
OTICE
!
The boiler may be installed on a
combustible floor; however, the
boiler must never be installed on
carpeting.
Bumping hazard from overhead
ducts! Install all components with
adequate vertical clearances.
Insufficient clearance can restrict
the service access, increasing the
possibility of injury.
Summary of Contents for SC-2000
Page 50: ...Gas Fired Boiler Harsco Industrial Patterson Kelley Technical Service 1 877 728 5351 50...
Page 52: ...Gas Fired Boiler Harsco Industrial Patterson Kelley Technical Service 1 877 728 5351 52...
Page 54: ...Gas Fired Boiler Harsco Industrial Patterson Kelley Technical Service 1 877 728 5351 54...