80-150 kW Frame & Header Kits Manual
6.2.4 INSTALLATION DRAWING WITH 2 - DN100 150 kW BOILERS (SIDE BY SIDE)
(OPTIONAL LOW LOSS HEADER SHOWN FOR INFORMATION)
(T
OP OF FR
A
ME)
1830
(T
OP OF BOILER)
1801
696
780
794
1480
239
569
250
500
123
SYSTEM FLOW
DN100 PN6 FLANGE
SYSTEM RETURN
DN100 PN6 FLANGE
1000
120
450
293
894
480
20
480
704
NOTE:
1. MIXING HEADER AND GAS CONNECTIONS CAN BE LOCATED
EITHER SIDE OF THE LHS OR RHS OF THE ASSEMBLY TO SUIT
THE INSTALLATION REQUIREMENTS.
2. OPTIONAL FRAME DN100 FLANGED PUMP (UIN 235596)
ONE PER BOILER.
3. OPTIONAL LOW LOSS HEADER (UIN 232877 DN100)
ONE PER CASCADE.
6.2.3 INSTALLATION DRAWING WITH 2 - DN80 80-120 kW BOILERS (SIDE BY SIDE)
(OPTIONAL LOW LOSS HEADER SHOWN FOR INFORMATION)
All dimensions in mm
All dimensions in mm