Figure 4.5.2 – Boiler Condensate Connection
4.5 Condensate Connections
Provision must be made for removal of condensate from the boiler and flue system.
Condense is mildly acidic, typically pH 3 - pH 5.
Condense pipework must be non-corrosive and not copper. Hamworthy recommend
32mm dia. Plastic waste pipe.
Condense may be discharged to a standard drain subject to National or Local
regulations.
Boiler Condensate
Connection
(32mm o/d)
Figure 4.5.1 - Boiler Condensate Pipework Connection
Location of condense
pipework should prevent
freezing within
tundishes, traps and
pipework.
Do not allow blockage or
damage to the
condensate trap.
The connection to the
boiler condense drain
accepts a straight push-
fit coupling for 32mm i.d.
plastic waste pipe.
Summary of Contents for Purewell VariHeat 70c
Page 2: ......
Page 43: ...HAMWORTHY HEATING LTD 37 PUREWELL VariHeat c 500001169 T Figure 8 3 11 Operating phases ...
Page 44: ...HAMWORTHY HEATING LTD 38 PUREWELL VariHeat c 500001169 T Figure 9 0 Boiler Wiring Schematic ...
Page 65: ...HAMWORTHY HEATING LTD 59 PUREWELL VariHeat c 500001169 T Figure E1 2 Typical Piping Layouts ...
Page 70: ...HAMWORTHY HEATING LTD 64 PUREWELL VariHeat c 500001169 T NOTES ...
Page 71: ......