Energy storage system assembly
Selecting a suitable assembly location with permissible environmental conditions
CAUTION!
The energy storage system must be permanently wired into the existing
building installation and meet the applicable national installation regulations
and legal provisions.
The manufacturer does not assume any liability in the event of non-compliance
with the assembly location requirements and permissible environmental
conditions.
ç
To optimally and safely operate the energy storage system, the following assembly location
requirements must be complied with:
–
No direct sunlight
–
Room temperature between 5 °C and 35 °C
–
No area subject to explosion hazards
–
No room subject to flooding
–
Dry room
–
No corrosive gases
–
No environment containing ammonia
–
No saline humidity
–
No heaters in the immediate vicinity of the assembly location
–
It is recommended to choose a well-ventilated assembly location to prevent heat accumu-
lation
–
Minimum room volume (generally designed for non-climatised interior room)
- With active room ventilation: 10 m³
- Without active room ventilation: 50 m³
–
Minimum space below, above and in front of the energy storage system in accordance
with specifications:
- below the energy storage system: min. 20 cm or base assembly
- above the energy storage system: min. 20 cm
- in front of the energy storage system: min. 80 cm
–
The maximum assembly height is 2,000 m above sea level.
Installations at greater altitudes must be requested from Hager and are possible if taking
into account derating factors.
–
If assembling the system in the living space, please note that the device may emit noise
during operation (fan noises, etc.) that may become a nuisance.
–
During installation, ensure that the energy storage system will not be mechanically im-
paired during installation or daily operation (e.g. by doors that hit against the energy stor-
age system when opening). Further measures for the mechanical protection of the energy
storage system may have to be implemented.
–
Emergency exits must be kept clear at all times
–
Applicable fire protection regulations must be complied with
–
An ABC fire extinguisher or carbondioxyde extinguisher should be available.
It is recommended to design the operating room in accordance with F30 (fire-retardant). and
flammable materials should not be stored in this room as this would increase the potential
risk.
The device must be installed so that it can be safely accessed for servicing. Do not place
items in the free space in front, behind and to the sides of the device.
flow
Energy storage system