CAUTION!
Should the unit be assembled at the customer, the maintenance unit is supplied without oil.
Before putting the unit into operation, the main air supply line must be cleaned and the oiler of the
maintenance unit must be filled with oil. Should this not be done the unit may be severely damaged.
Pos: 13.2.3.4 /1_HADEF/---ALLGEMEIN/Hinweise/Druckluft/VORSICHT - Wartungseinheiten sind nicht für synthetisches Öl zugelassen. @ 1\mod_1185783956354_52.docx @ 7447 @ @ 1
CAUTION!
The maintenance units are not approved for use with synthetic oil.
They must not be connected to compressed air systems which are supplied by compressors with synthetic
lubricants.
Pos: 13.2.4.1 /1_HADEF/9--INBETRIEBNAHME/Allgemein/Getriebe/05.Getriebe - Sonstige @ 0\mod_1175600728406_52.docx @ 3050 @ @ 1
9.3 Gear
Should the gear not be closed, the level of lubricant must be checked before putting the device into
operation.
Pos: 13.2.4.2 /1_HADEF/---ALLGEMEIN/Hinweise/HINWEIS - Verschluss-Entlüftungsschraube @ 1\mod_1259676576858_52.docx @ 11347 @ @ 1
NOTICE!
For transport, some gear types are fitted with a plug screw. Replace the plug screw by a ventilation screw
(attached) before putting the unit into operation.
Pos: 13.2.5.1 /1_HADEF/9--INBETRIEBNAHME/Allgemein/Drahtseil/05.Drahtseil @ 0\mod_1172571056093_52.docx @ 369 @ @ 1
9.4 Wire
rope
Wire ropes must be free from corrosion, dirt or damage.
They must be lubricated before commissioning.
No lubrication shortens the lifetime of the wire rope and the maintenance intervals.
Pos: 13.2.5.2 /1_HADEF/---ALLGEMEIN/Hinweise/Seile/WARNUNG - Kunststoffseile verboten @ 0\mod_1177329455688_52.docx @ 5225 @ @ 1
WARNING!
It is not allowed to use plastic wire ropes or plastic-coated wire ropes.
Pos: 13.2.6.1 /1_HADEF/9--INBETRIEBNAHME/Allgemein/Seilwegbegrenzungsschalter E+P/06.Seilwegbegrenzungsschalter @ 0\mod_1175603073634_52.docx @ 3064 @ @ 1
9.5
Limit switch for wire rope path (as option)
The limit switch (if exist) must be adjusted before commissioning and after maintenance work has been
made. Intermediate checks for correct function are necessary.
The switching point for the upper load position must be set in such a way that even in case of unfavourable
cable winding the permitted highest load position is not overrunned. In individual cases it may be necessary
for the customer to install an external emergency switch. The limit switch for the lowest load position is
always driven exactly independently of the cable length.
Pos: 13.2.6.2 /1_HADEF/---ALLGEMEIN/Hinweise/Endschalter/HINWEIS - Genaues Anfahren Endschalter @ 0\mod_1177487083967_52.docx @ 5407 @ @ 1
NOTICE!
An exact driving up to the upper end position is only possible in the first wire rope layer with grooved rope
drum.
Exactness decreases with larger wire rope length and several wire rope layers.
Pos: 13.2.7.1 /1_HADEF/9--INBETRIEBNAHME/Allgemein/Schlaffseilschalter E+P/07.Schlaffseilschalter @ 0\mod_1175767622185_52.docx @ 3388 @ @ 1
9.6
Slack rope switch (as option)
In case of slack rope i.e. by setting down of the load, the slack rope switch prevents further unwinding of the
wire rope.