Item 

Requirements 

Result 

the equipment room. 

 

There is a minimum clearance of 1200 mm 
(47.24 in) between the rack and walls or other 
devices. 

Ventilation 

 

There is a minimum clearance of 300 mm 
(11.81 in) around the inlet and outlet air vents. 

 

A good ventilation system is available at the 
installation site. 

 

Power supply 

 

The power supply system can output enough 
power to maintain the device operation. 

 

An uninterrupted power supply (UPS) is 
available. 

 

The power-off switch in the equipment room is 
located so that the power can be immediately 
shut off when an accident occurs. 

 

Grounding 

 

The grounding specifications for the 
equipment room comply with national and 
industry standards. 

 

All communication devices in the equipment 
room are reliably grounded. 

 

The working earthing and protective earthing 
systems of the communication power supplies 
use the same earthing conductor set with the 
protective earthing system of the 
communication devices. 

 

Temperature 

0°C to 45°C (32°F to 113°F). 

 

Humidity 

5% RH to 95% RH (noncondensing). 

 

Cleanliness 

 

Dust concentration ≤ 3 × 104 particles/m

3

 

No visible dust on desk within three days. 

 

EMI prevention  

 

Take effective measures to protect the power 
system from the power grid system. 

 

Separate the operation ground of the gateway 
from the grounding device or lightning 
protection grounding device as far as 
possible. 

 

Keep the gateway far away from radio 
stations, radar and high-frequency devices 
working in high current. 

 

Use electromagnetic shielding when 
necessary. 

 

Safety precautions 

 

The gateway is far away from any heat source 
and moist area. 

 

The emergency power switch in the 
equipment room is located. 

 

Accessories 

Installation accessories provided with the gateway.   

Reference 

 

Documents shipped with the gateway. 

 

Online documents. 

 

 

Summary of Contents for SecPath M9000-AI-E8

Page 1: ...tions 1 Electricity safety 1 Handling safety 1 ESD prevention 1 Laser safety 2 Examining the installation site 2 Weight support 2 Space 2 Cooling 3 Power 4 Lightning protection 5 Temperature 5 Humidit...

Page 2: ...ngrounded power extension cables missing safety grounds and wet floors Locate the emergency power off switch in the room before installation so you can quickly shut power off when an electrical accide...

Page 3: ...sure the floor can support the total weight of the rack chassis and accessories Additionally the floor loading plan must also consider system expansion such as adding more modules For more information...

Page 4: ...e screw of the fan tray at the chassis rear Figure 1 Rack dimensions Cooling The gateway uses front to rear airflow for heat dissipation Plan the installation site for the gateway based on its airflow...

Page 5: ...t voltage is stable and within the acceptable range allowed by the gateway Enough batteries are available to ensure uninterrupted device operation in the event of a power failure For the power supply...

Page 6: ...to a high temperature environment dry the chassis before powering it on to avoid short circuits If the temperature in the equipment room is too high too low or changes dramatically the device reliabi...

Page 7: ...ents as shown in Table 5 Table 5 Harmful gas limits in an equipment room Gas Max mg m 3 SO2 1 0 H2S 0 5 NH3 3 0 Cl2 0 3 NO2 1 0 EMI Electromagnetic interference EMI might be coupled from the source to...

Page 8: ...ies Pre installation checklist Table 6 Pre installation checklist Item Requirements Result Installation site Load bearing The floor or ground at the installation site can support the sum of the weight...

Page 9: ...rotective earthing systems of the communication power supplies use the same earthing conductor set with the protective earthing system of the communication devices Temperature 0 C to 45 C 32 F to 113...

Reviews: