5 Final checks
BS-01
Final checks
•
After completing installation of the system, check again
that all joints and pipes are properly tightened and not
leaking.
•
Check that all covers are fitted and secured.
•
Check that the fitting of all connections (water, flue,
electrical, ...) has been done correctly.
•
Check that all required safety signs and instructions are
attached and hand over all documentation (operating and
installation instructions) for the system.
•
Check that all electrical connections have been properly
wired before connecting the system to the power supply.
•
Clean the system and clear up the installation site.
•
Always leave the boiler room clean.
Initial commissioning Commissioning must only be carried out by GUNTAMATIC or
a qualified specialist. The precondition is that the flue
technician, heating installer and electrician have cleared the
system for operation. The authorised GUNTAMATIC specialist
will carry out the following work during commissioning:
•
Check the entire system
•
Check the electrical functions
•
Adjust the programmer to the system
•
Commission the system
•
Explain to the user how the system functions and how to
operate and clean it
•
Record the details of the customer and the system and
complete the commissioning log
Any deficiencies identified must be recorded in
writing and rectified within the following 4 weeks
in order to maintain guarantee entitlement.
The fully completed commissioning checklist must
be sent to GUNTAMATIC immediately as
otherwise the guarantee will be void.
These installation instructions should not be
destroyed after commissioning but kept
permanently with the system together with the
operating instructions.